BLD98-02099
| INSP - Framing/Rough-in | 9/11/1998 | 9/11/1998 | 9/14/1998 12:00:00 AM | P | PASS |
|
|
09/11/98 407 - Scheduled by Hello!. Contact phone is [8676771].
|
BLD98-02421
| INSP - Foundation | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | | PART |
|
|
/ / 407 - Time now 4;45pm job has been completed and is now being poured,exposed sections of rebar are at 24" o.c. vert and horiz,exposed sections apear ok, Boise City does not require any rebar in the basement walls so it exceeds Boise City requirements.
|
BLD98-01843
| INSP - Footings | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | | PART |
|
|
no plans at site,footings are 16" wide for the basement on called contractor,said he is unable to get the plans out to job rained on,wants to pour at own risk,said he will cal me with plans on site for the other portions of the footings,said the footings at site are as per the approved plans. / / 407 - re-inspection,no one at site called contractor.
|
BLD98-01590
| INSP - Letter of compliance | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | | PASS |
|
|
/ / 407 - LC#15938
|
BLD98-01590
| INSP - Letter of compliance | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | | PASS |
|
|
/ / 407 - LC#15938
|
MEC98-01232
| INSP - Framing/ Rough-in | 9/9/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | A | FAIL |
|
|
09/11/98 407 - left corrections also no ga spipeing ready at this time.w
|
BLD98-01085
| INSP - Final | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | A | FAIL |
|
|
09/11/98 407 - left corrections.
|
BLD98-01997
| INSP - Framing/Rough-in | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | A | FAIL |
|
|
09/11/98 407 - Scheduled by Hello!. Contact phone is [8666175].
|
BLD98-01719
| INSP - Framing/Rough-in | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | A | FAIL |
|
|
09/11/98 407 - left corrections posted .
|
BLD98-02551
| INSP - Foundation | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | A | CANC |
|
|
09/11/98 407 - transfer to Wes worchester.
|
BLD98-02151
| INSP - Wall cover | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | A | FAIL |
|
|
09/11/98 407 - fail.
|
BLD98-02421
| INSP - Foundation | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | NR |
|
|
09/11/98 407 - Still need to set up some lower rear form boards,told the contractor i will try to come back later when job was completed, time now 1;30.
|
BLD98-01828
| INSP - Framing/Rough-in | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | NR |
|
|
09/11/98 407 - not ready.
|
BLD98-01502
| INSP - Framing/Rough-in | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | PASS |
|
|
09/11/98 407 - HAROLD ###-#### SHEAR WALL INSPECTION
|
BLD98-01590
| INSP - Final | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | PASS |
|
|
09/11/98 407 - Scheduled by Hello!. Contact phone is [8912222].
|
BLD96-02798
| INSP - Final | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | PART |
|
|
09/11/98 407 - only has 1 correction at the center stairs.
|
BLD97-02488
| INSP - Framing/Rough-in | 9/10/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | PART |
|
|
09/11/98 407 - ok to occupie small section at corner as on plan.
|
BLD98-01606
| INSP - Framing/Rough-in | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | CANC |
|
|
09/11/98 407 - JOHN ###-#### REINSPECTION AND ENERGY CODE COMPLIANCE
|
BLD98-01648
| INSP - Framing/Rough-in | 9/11/1998 | 9/11/1998 | 9/11/1998 12:00:00 AM | P | PART |
|
|
09/11/98 407 - one correction.R-IN INSP
|