Inspections for the day of: Thursday, September 11, 2008.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00239 INSP-Sprinkler Rough-in9/10/20089/11/20089/15/2008 4:39:55 PMAPART
See locations on approved plan set sheet FP5 for locations inspected to date on the 1st floor only, including areas north of the corridor main, noted issues in need of revision clouded and annotated.
FIR08-00597 INSP-Sprinkler Rough-in9/11/20089/11/20089/11/2008 3:50:10 PMPPART
Overhead installation at the grid ceiling is good for cover, atrium work is not finished.
BLD08-00379 FIRE-Final Inspection9/11/20089/11/20089/11/2008 3:48:16 PMPCANC
Incorrect permit number request.
FIR08-00610 INSP-Final Inspection9/11/20089/11/20089/11/2008 2:38:04 PMPFAIL
Sprinkler protection at the storage room exceeds 130 ft2, see approved plans for intended head layout. The remainder of work per this permit scope is okay for ceiling cover.
FIR08-00493 INSP-Sprinkler Rough-in9/11/20089/11/20089/11/2008 2:34:30 PMPPART
OH modifications are approved for cover at the drop ceilings per site inspection by T. Cobbley.
FIR08-00542 INSP-Final Inspection9/10/20089/11/20089/11/2008 1:37:31 PMAFAIL
Added heads below the ductwork need to match response type within the same fire area.
FIR08-00552 INSP-Alarm Testing9/10/20089/11/20089/11/2008 1:35:51 PMAPASS
Fire alarm work completed acceptable, field inspection passed, one relocated duct detector tested okay, a/v appliance heights AFF adjusted to comply with NFPA 72 req.
FIR08-00260 INSP-Alarm Testing9/10/20089/11/20089/11/2008 1:32:07 PMAPASS
Fire alarm system modifications tested satisfactory.
FIR07-00928 INSP-Sprinkler Rough-in/Hydro9/11/20089/11/20089/11/2008 11:27:00 AMAPART
Antifreeze system piping and drops at the 7th floor exterior balcony soffits above the patio areas only approved for cover with the exception of two heads to be relocated at the SW and NW corners due to spacing issues as discussed.
BLD08-00430 FIRE-Final Inspection9/11/20089/11/20089/11/2008 10:41:11 AMPPASS
Fire life safety finaled.
BLD08-00430 FIRE-Alarm Testing9/10/20089/11/20089/11/2008 10:40:43 AMADONE
Project fire alarm testing has been completed.
BLD08-01452 FIRE-Final Inspection9/10/20089/11/20089/11/2008 10:22:43 AMAPASS
Scope of repair work completed acceptable, corrections provided, life safety inspection passed.
BLD08-00980 FIRE-Final Inspection9/10/20089/11/20089/11/2008 9:38:25 AMAPASS
Fire life safety passed field inspection, signature card was not available on site.