FIR08-00367
| FIR-Aging Inspection | 9/11/2008 | 9/11/2008 | 9/12/2008 2:55:15 PM | | NR |
|
|
Per Robert Spinden Idaho Power is still in the process of installing duct smoke detectors.
|
FIR08-00410
| INSP-Sprinkler Rough-in/Hydro | 9/10/2008 | 9/11/2008 | 9/11/2008 3:46:32 PM | P | PASS |
|
|
The underground hydro test passed
|
FIR08-00563
| INSP-Sprinkler Rough-in/Hydro | 9/10/2008 | 9/11/2008 | 9/11/2008 2:57:24 PM | A | FAIL |
|
|
This inspection was for the cover of the piping above the restrooms on the second floor. The piping can not be covered until the existing insulation is re-attached to the roof deck and sprinkler protection is provided in the pipe chase between the two restrooms. I also spoke to Todd about resubmittals showing all of the additional upright heads addded due to full height walls.
|
FIR08-00188
| INSP-Sprinkler Rough-in/Hydro | 9/10/2008 | 9/11/2008 | 9/11/2008 12:09:34 PM | A | PASS |
|
|
Forward Flow Test passed
|
BLD08-01880
| FIRE-Final Inspection | 9/10/2008 | 9/11/2008 | 9/11/2008 11:13:27 AM | A | PART |
|
|
Provide corrected sprinkler coverage as discussed and provide approved single action hardware on the north exit door.
|