Inspections for the day of: Tuesday, September 11, 2018.
Number of inspections: 24
Percentage of inspections complete: 96 %
Percentage of inspections not complete: 4 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-00229 BLD-Framing/Rough-in9/4/20189/4/2018 P 
Jerimy Phone #: ###-####
BLD18-01488 FIRE-Final Inspection9/11/20189/11/20189/11/2018 4:04:48 PMPFAIL
Larry Phone #: ###-####. Provide current annual inspection fro fire extinguidhers. Provie ADA hardware on sliding doors. Coorection notice issued.
BLD18-01278 BLD-Framing/Rough-in9/7/20189/11/20189/11/2018 3:22:33 PMPCANC
Gene Phone #: ###-####
BLD18-01278 BLD-Wall Bracing9/11/20189/11/20189/11/2018 3:22:27 PMPPART
Gene Phone #: ###-####. Needs to block and nail addition.
BLD18-01737 BLD-Final9/11/20189/11/20189/11/2018 3:02:15 PMPPASS
Phone #: 2085904252 >> Inspection requested via mobile web by Jon craft. Ok for prem occ.
BLD18-01737 FIRE-Final Inspection9/11/20189/11/20189/11/2018 3:01:58 PMPPASS
Phone #: 2085904252 >> Inspection requested via mobile web by Jon craft. Life safety ok for final. The project related fire sprinkler has been finaled by Forest France and fire alarm by Lee Merideth.
BLD16-04475 BLD-Final9/11/20189/11/20189/11/2018 2:18:08 PMPPASS
Phone #: ###-#### Inspection requested via web by Sam Brown
BLD16-04475 DOC - Permit Finaled9/11/20189/11/20189/11/2018 2:18:01 PMPPASS
All isues have been repaired.
BLD18-01191 BLD-Other9/10/20189/11/20189/11/2018 2:06:19 PMPNR
roof decking - Jeff Phone #: ###-####
BLD18-01191 BLD-Wall Bracing9/11/20189/11/20189/11/2018 2:06:12 PMPPASS
roof decking - Jeff Phone #: ###-####. West exterior wall is know ok to cover.
BLD18-02304 BLD-Footing9/10/20189/11/20189/11/2018 1:23:10 PMPCANC
Stem wall, early PM, pouring at 2 - Jason Phone #: ###-####
BLD18-02304 BLD-Foundation9/11/20189/11/20189/11/2018 1:23:04 PMPPASS
Stem wall, early PM, pouring at 2 - Jason Phone #: ###-####
BLD18-02617 BLD-Framing/Rough-in9/7/20189/11/20189/11/2018 11:12:51 AMANR
Kevin is the on-site PM Phone #: ###-#### Inspection requested via web by Tom Noeker. Needs mech. rough in inspection prior to framing inspection.
BLD18-00270 BLD-Final9/10/20189/11/20189/11/2018 11:11:41 AMANR
Phone #: ###-#### Inspection requested via web by kevin debelloy. Needs mech final first.
BLD18-02290 BLD-Conference9/9/20189/11/20189/11/2018 10:34:30 AMANR
Wall Bracing and Framing Phone #: ###-#### Inspection requested via web by Petros Paflias. Will need to go back to plan review to show changes in exterior door and windows as well as approval for site built trusses.
BLD18-01728 BLD-Footing9/10/20189/11/20189/11/2018 10:04:28 AMAPASS
Request early inspection. Concrete is will called for 10 am. We can adjust to suit your schedule Phone #: ###-#### Inspection requested via web by Ben Sears. Lower level footings only, excluding exterior columns.
BLD17-00566 BLD-Final9/10/20189/11/20189/11/2018 9:17:14 AMAPASS
Please call 30 min prior to inspection. Phone #: ###-#### Inspection requested via web by John Saucerman. the panic hardware has been installed. ok for perm occ.
ESC18-00624 Site Final9/11/20189/11/20189/11/2018 9:03:15 AMADONE
ESC18-00624 DOC - Permit Finaled9/11/20189/11/20189/11/2018 9:03:07 AMPPASS
BLD18-01424 BLD-Final9/11/20189/11/20189/11/2018 9:02:56 AMAPASS
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD18-01424 DOC - Permit Finaled9/11/20189/11/20189/11/2018 9:02:48 AMPPASS
BLD18-01424 BLD-Blower Door Test Results9/11/20189/11/20189/11/2018 9:00:48 AMADONE
4.5ACH @50pa
BLD18-03209 FIRE-Final Inspection9/10/20189/11/20189/11/2018 8:36:17 AMAPASS
All issues have been resolved. ok for perm occ.
BLD18-01390 BLD-Foundation9/10/20189/11/20189/10/2018 4:07:42 PMACANC
Late am if possible. Thank you. We hope to pour at 2 pm. Phone #: ###-#### >> Inspection requested via web by Sean Worthington Inspection cancelled from web by: Sean Worthington