FIR18-00389
| INSP-Final Inspection | 9/11/2018 | 9/11/2018 | 9/12/2018 12:00:00 AM | P | PASS |
|
|
I''ll have Shane meet you at the B.17c desk. Phone #: ###-#### >> Inspection requested via web by John Wheeler
______________________
Installation was ok.
|
FIR17-00616
| INSP-Final Inspection | 9/11/2018 | 9/11/2018 | 9/12/2018 12:00:00 AM | P | FAIL |
|
|
Chris will take you to B.51 Phone #: ###-#### >> Inspection requested via web by John Wheeler
___________
The drawing did not correlate with the installation. Revised drawings are required.
|
FIR17-00743
| INSP-Final Inspection | 9/11/2018 | 9/11/2018 | 9/12/2018 12:00:00 AM | P | PASS |
|
|
B.51 Phone #: ###-#### >> Inspection requested via web by John Wheeler
__________
Installation was OK
|
FIR18-00118
| INSP-Final Inspection | 9/11/2018 | 9/11/2018 | 9/12/2018 12:00:00 AM | P | PASS |
|
|
B.51 Phone #: ###-#### >> Inspection requested via web by John Wheeler
______________
Installation was ok.
|
FIR18-00226
| INSP-Final Inspection | 9/11/2018 | 9/11/2018 | 9/12/2018 12:00:00 AM | P | PASS |
|
|
B.51 Phone #: ###-#### >> Inspection requested via web by John Wheeler
_______________
Installation was ok.
|
FIR18-00667
| INSP-Sprinkler Rough-in | 9/11/2018 | 9/11/2018 | 9/12/2018 12:00:00 AM | P | PASS |
|
|
rick fry Phone #: ###-#### >> Inspection requested via web by Brodie Stenquist
_____________
Rough in was ok.
|
FIR16-00563
| INSP-Sprinkler Rough-in/Hydro | 9/10/2018 | 9/11/2018 | 9/11/2018 12:00:00 AM | A | PASS |
|
|
this is an underground hydro. Lonnie is our foreman Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt
I also looked at the underground in the parking garage. All was ok. Hydro of underground OK.
|
FIR13-00682
| INSP-Final Inspection | 9/10/2018 | 9/11/2018 | 9/10/2018 3:36:13 PM | P | CANC |
|
|
Building access is open, inspection technician is Ray McQueen Phone #: ###-#### >> Inspection requested via web by Rose Peterson Inspection cancelled from web by: Rose Peterson
|