Inspections for the day of: Monday, September 12, 2005.
Number of inspections: 4
Percentage of inspections complete: 75 %
Percentage of inspections not complete: 25 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR04-00004 INSP-Conference8/17/20059/6/2005 P 
Follow up for inspection
FIR05-00259 INSP-Sprinkler Rough-in/Hydro9/12/20059/12/20059/12/2005 3:34:29 PMPPART
See approved plans for locations of remaining deficiencies. Also still need head wrench, sign on control valve and forward flush
FIR04-00684 INSP-Sprinkler Rough-in/Hydro9/12/20059/12/20059/12/2005 12:43:27 PMAPART
Main lobby is ok to cover. Basement east side of main corridor is ok to cover.
MIS05-00135 FIR-Final9/9/20059/12/20059/12/2005 8:55:22 AMAPASS
fire life safety finaled