FIR06-00813
| INSP-Alarm Testing | 9/12/2007 | 9/12/2007 | 9/13/2007 7:39:48 AM | P | DONE |
|
|
The fire alarm panel manufacturer, phone lines and supervision of NAC 4 and NAC 5 were verified. The smoke detector in the facp room and down the corridor as marked on the plans were tested. I found that the smoke detector and audio/visual were both overspaced from the end of the corridor. Also a NAC panel has been added in the facp room. Plans need to be resubmitted showing the new NAC. The facp was in trouble due to missing monitor modules at the roof top units. I went over requirements with the owner, building contractor, electrical contractor and fire alarm contractor.
|
BLD07-01530
| FIRE-Final Inspection | 9/12/2007 | 9/12/2007 | 9/13/2007 7:34:56 AM | P | PASS |
|
|
Life safety passed.
|
FIR07-00602
| INSP-Sprinkler Rough-in | 9/12/2007 | 9/12/2007 | 9/13/2007 7:34:15 AM | P | CANC |
|
|
The second floor piping can be covered. A sprinkler head needs to be added in the small triangular closet in the reception area.
|
FIR07-00534
| INSP-Final Inspection | 9/11/2007 | 9/12/2007 | 9/12/2007 3:22:08 PM | P | CANC |
|
|
Please call 1/2 hour prior to inspection. Brian is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
FIR06-00988
| INSP-Sprinkler Rough-in/Hydro | 9/12/2007 | 9/12/2007 | 9/12/2007 2:44:32 PM | P | PASS |
|
|
The underground hydro test passed for both lines.
|
BLD05-00633
| FIRE-Final Inspection | 9/12/2007 | 9/12/2007 | 9/12/2007 2:36:30 PM | P | CANC |
|
|
I spoke to wayne by phone and told him that I would not do the life safety inspection until the fire alrm and sprinklers were complete.
|
BLD07-01704
| FIRE-Conference | 9/11/2007 | 9/12/2007 | 9/12/2007 2:32:20 PM | A | FAIL |
|
|
Drove to the job site but contractor was not there. I left a message on his phone.
|
FIR07-00610
| INSP-Final Inspection | 9/12/2007 | 9/12/2007 | 9/12/2007 12:01:47 PM | A | PASS |
|
|
permit finaled
|
FIR07-00678
| INSP-Final Inspection | 9/11/2007 | 9/12/2007 | 9/12/2007 11:43:06 AM | A | PASS |
|
|
Permit finaled
|
FIR07-00696
| INSP-Sprinkler Rough-in | 9/11/2007 | 9/12/2007 | 9/12/2007 11:13:06 AM | A | PASS |
|
|
Sprinkler piping is ok to cover. One additional hanger is required in the backroom.
|
FIR07-00756
| INSP-Sprinkler Rough-in | 9/11/2007 | 9/12/2007 | 9/12/2007 10:58:12 AM | A | PART |
|
|
The 5'-0" stub out is ok to cover. As measured it does not have the 4'-6" required bury. The top of pipe is 6'-2" from the top of the foundation. The general contractor assured me that once the finish grade and landscaping is complete the piping would have the required 4'-6" bury. If it does I notified him it would need to be dug up and installed at the correct depth.
|
FIR07-00642
| INSP-Sprinkler Rough-in | 9/11/2007 | 9/12/2007 | 9/12/2007 10:55:37 AM | A | PASS |
|
|
See the city approved plans for piping in the womens clothing area that is ok to cover.
|
FIR07-00758
| INSP-Sprinkler Rough-in/Hydro | 9/11/2007 | 9/12/2007 | 9/12/2007 10:54:34 AM | A | PART |
|
|
The mens restroom sprinkler piping is ok to cover. The womens area is not done yet. Sprinkler penndants are overspaced in the coffee shop area.
|