MEC11-02720
| Rough-in | 9/12/2011 | 9/12/2011 | 9/12/2011 4:30:31 PM | P | FAIL |
|
|
Builder is delivering approved Wight Soft Phone #: ###-#### >> Inspection requested via web by Dustin Rich balanced dampers are required to be at take-offs or branch fitting, need insulation shield to b-vent
|
MEC11-02849
| Pressure Test | 9/12/2011 | 9/12/2011 | 9/12/2011 3:27:13 PM | P | PASS |
|
|
25# test
|
MEC11-02849
| Rough-in | 9/12/2011 | 9/12/2011 | 9/12/2011 3:26:34 PM | P | FAIL |
|
|
Please complete rough in and pressure test. This house is being crawled today so after 3 would be great if not available then please contact eric. Phone #: ###-#### >> Inspection requested via web by Jillian Andrews suport furnace flue to structure, pressure test and duct blast test ok
|
MEC11-01949
| Conference | 9/10/2011 | 9/12/2011 | 9/12/2011 2:44:17 PM | P | DONE |
|
|
Phone #: ###-#### >> Inspection requested via web by Mike Almanza
|
MEC11-01949
| Final | 9/12/2011 | 9/12/2011 | 9/12/2011 2:43:56 PM | P | PASS |
|
|
|
MEC11-02059
| Final | 9/12/2011 | 9/12/2011 | 9/12/2011 2:43:18 PM | P | PASS |
|
|
|
MEC11-01898
| Final | 9/10/2011 | 9/12/2011 | 9/12/2011 2:29:26 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Mike Almanza
|
MEC11-01805
| Final | 9/12/2011 | 9/12/2011 | 9/12/2011 2:29:06 PM | P | PASS |
|
|
|
MEC11-00559
| Mec-Aging Inspection | 9/12/2011 | 9/12/2011 | 9/12/2011 2:02:34 PM | | FAIL |
|
|
contractor has not scheduled final inspection
|
MEC11-02854
| Final | 9/12/2011 | 9/12/2011 | 9/12/2011 2:00:28 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Amanda Drake
|
MEC11-02847
| Final | 9/12/2011 | 9/12/2011 | 9/12/2011 1:45:57 PM | P | PASS |
|
|
As early as possible in the afternoon please. Thanks! Phone #: ###-#### >> Inspection requested via web by April Sims
|
MEC11-02755
| Final | 9/12/2011 | 9/12/2011 | 9/12/2011 1:28:19 PM | P | FAIL |
|
|
Call Gary with any questions. Phone #: ###-#### >> Inspection requested via web by Rhonda Marcum gas line to units on roof not complete
|
MEC11-02767
| Conference | 9/12/2011 | 9/12/2011 | 9/12/2011 10:10:44 AM | A | DONE |
|
|
test
|
MEC11-02424
| Conference | 9/12/2011 | 9/12/2011 | 9/12/2011 10:09:20 AM | P | PASS |
|
|
test
|