ELE18-02598
| Final | 9/12/2018 | 9/12/2018 | 9/12/2018 5:13:13 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Alan Lusk 110.3- Items shall be connected as per manufacturers instructions. Level 3 bath GFI has reverse polarity, Level 1 understair light not working. 210.8- Washer receptacle is located with in 6' of a sink and shall be GFCI protected. 210.12- Level 1 room has closet with clothes rod installed so shall have AFCI protected. 314.20- Where boxes installed in a wall with non combustible materials they shall not be set back more than 1/4" from surface with out box extensions installed. Kitchen counter receptacles. 348.30- FMC shall be secured with in 12" of each box. Disposal
|
ELE18-01206
| Electrical Rough-In | 9/11/2018 | 9/12/2018 | 9/12/2018 4:00:03 PM | A | CANC |
|
|
Please call Chris for inspection of 1st floor walls. As close to 1PM as possible please.
Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Unable to inspect job prior to crew leaving for the day. Called contact he stated OK would reschedule for next day.
|
ELE18-02183
| Final | 9/12/2018 | 9/12/2018 | 9/12/2018 3:57:35 PM | P | PASS |
|
|
Please call Ron upon arrival at the 17C lobby. Phone #: ###-#### Inspection requested via web by Ron Pontius BLDG 15 room 106A build out. South wall added and floor receptacles. All wiring for future tools covered on blanket permit. Final ok
|
ELE18-03292
| Electrical Rough-In | 9/12/2018 | 9/12/2018 | 9/12/2018 3:19:47 PM | P | PASS |
|
|
We need a wall rough, Tobias is the contact. Thank you Phone #: ###-#### Inspection requested via web by Stacie Tasker Walls rough in ok cover
|
ELE18-03490
| Electrical Rough-In | 9/12/2018 | 9/12/2018 | 9/12/2018 2:58:28 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brad Girard All areas walls and hardlids rough in ok cover
|
ELE18-02623
| Rough-In Permanent Service | 9/12/2018 | 9/12/2018 | 9/12/2018 2:30:51 PM | P | PASS |
|
|
ready now Phone #: ###-#### Inspection requested via web by Bob Glenn Level 3 slider not in place, print shows 3 panel door. If any of the panels are fixed receptacle spacing may be in violation. Rough in ok cover p/s u/g n ok
|
ELE18-03488
| Temporary Service | 9/11/2018 | 9/12/2018 | 9/12/2018 2:10:21 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson t/s u/g n ok
|
ELE18-03489
| Temporary Service | 9/11/2018 | 9/12/2018 | 9/12/2018 2:09:52 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson t/s u/g n ok
|
ELE18-03253
| Electrical Rough-In | 9/11/2018 | 9/12/2018 | 9/12/2018 1:21:29 PM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Wren Van Bockel 110.27- All wiring located below 8' shall be protected from physical damage. Horizontal runs of NM cable shall be protected. 210.8(A)(2)- All 120 volt 15 and 20 amp receptacle outlets located in storage shed shall have GFCI protection. 250.32(B)- All non-current carrying metal parts shall not be connected to grounded conductor on load side of main disconnect. Seperate grounds and neutrals on shed sub panel. 250.64- Grounding electrode conductor shall be terminated at service location. Owner stated was going to have Idaho Power terminate them, informed they will not terminate any other conductors not associated with line side. 300.12- PVC from service to shed shall be a complete system. LB not secured to panel. Reducing washers needed and lock nuts and bushing. 334.30- NM cable shall be secured with in 12" of panel terminations.
|
ELE17-01337
| Final | 9/11/2018 | 9/12/2018 | 9/12/2018 12:12:50 PM | A | PASS |
|
|
Rescheduled final inspection. Contact is Rick Badley. If possible please notify Rick 30 minutes prior to arriving on site. Thank you. Phone #: ###-#### Inspection requested via web by Clint Tate Final ok
|
ELE18-03438
| Final | 9/11/2018 | 9/12/2018 | 9/12/2018 11:40:16 AM | A | PASS |
|
|
Ceiling-Final Call Dave Forbes ahead of inspection to meet . Phone #: ###-#### Inspection requested via web by Harvey Reyna Final ok
|
ELE18-03438
| Electrical Rough-In | 9/12/2018 | 9/12/2018 | 9/12/2018 11:39:54 AM | P | PASS |
|
|
Ceiling-Final Call Dave Forbes ahead of inspection to meet . Phone #: ###-#### Inspection requested via web by Harvey Reyna Circuits to food coolers and counter out in dining area with portable warmers used. No vending machines installed. Rough in ok cover
|
ELE18-03493
| Permanent Service | 9/12/2018 | 9/12/2018 | 9/12/2018 10:46:04 AM | P | PASS |
|
|
Contact: Josh Mangum Phone #: ###-#### Inspection requested via web by Deb Gooden Permit to check out equipment damaged by Knitting Factory damage mostly to mezzanine to offices located above. Electrical room at mezzanine level wet from putting out fire and has branch circuit damage. Contactor to lockout all associated with knitting factory. Idaho power to energize main gear and electrical contractor to verify each tenant space feeders ok prior to energizing. p/s u/g rec ok
|
ELE18-03201
| Final | 9/11/2018 | 9/12/2018 | 9/12/2018 8:30:37 AM | A | PASS |
|
|
final Phone #: ###-#### Inspection requested via web by David Feller Final ok
|
ELE18-03201
| Electrical Rough-In | 9/11/2018 | 9/12/2018 | 9/12/2018 8:29:52 AM | A | PASS |
|
|
Re inspection of ceiling Phone #: ###-#### Inspection requested via web by David Feller Grid rough in ok cover
|