BLD10-00924
| FIRE-Final Inspection | 9/10/2010 | 9/13/2010 | 9/13/2010 3:29:46 PM | P | FAIL |
|
|
Provide panic hardware at three locations, post signage at the door to the FACP room, post one fire extinguisher at the basement mechanical room per review notes, remove one non-functional SD at the west stairway, provide approved plan mod reflecting the scope of work not including the new addition incomplete at this time. Project finishes underway.
|
FIR10-00338
| INSP-Final Inspection | 9/13/2010 | 9/13/2010 | 9/13/2010 3:24:54 PM | P | PART |
|
|
Final pending control valve supervision at the spray booth.
|
FIR10-00401
| INSP-Final Inspection | 9/10/2010 | 9/13/2010 | 9/13/2010 3:23:40 PM | P | PASS |
|
|
Fire alarm work passed inspection, permit final approved.
|
BLD10-01600
| FIRE-Final Inspection | 9/10/2010 | 9/13/2010 | 9/13/2010 3:22:51 PM | A | PASS |
|
|
Correction notice items verified for completion. Life safety finaled.
|
BLD10-00664
| FIRE-Final Inspection | 9/10/2010 | 9/13/2010 | 9/13/2010 3:21:44 PM | A | PASS |
|
|
Final fire life safety inspection completed acceptable, two missing escutcheons at the metrology lab to be replaced as discussed.
|
BLD10-02162
| FIRE-Final Inspection | 9/10/2010 | 9/13/2010 | 9/13/2010 3:20:04 PM | P | PASS |
|
|
Noted corrections including power at one EM light and one exit sign, door hardware and posted fire extinguishers are complete. Life safety inspection passed.
|