Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD10-01246 FIRE-Final Inspection9/13/20109/13/20109/13/2010 1:34:19 PMPPASS
Life safety passed. The building inspector is going to verify the exit discharge lighting.
FIR10-00431 INSP-Final Inspection9/13/20109/13/20109/13/2010 1:27:12 PMPPASS
permit finaled
FIR10-00430 INSP-Final Inspection9/13/20109/13/20109/13/2010 1:22:16 PMAPASS
permit finaled
FIR10-00395 INSP-Final Inspection9/10/20109/13/20109/13/2010 1:17:26 PMAFAIL
The duct smoke detector is being used for fire/smoke damper operation which is outside of the duct smoke detectors listing since it is not listed to 0cfm. I spoke to Randy on site and Mike in the office. No testing was performed.
BLD10-01588 FIRE-Final Inspection9/10/20109/13/20109/13/2010 11:47:29 AMAFAIL
Provide correct address and provide single action lever hardware on the doors as marked on the plans as discussed.
BLD10-00973 FIRE-Final Inspection9/10/20109/13/20109/13/2010 10:53:13 AMAPASS
Life safety passed.
BLD06-02048 FIRE-Final Inspection9/10/20109/13/20109/13/2010 10:52:03 AMAPASS
life safety already passed.
BLD10-01246 FIRE-Final Inspection9/10/20109/13/20109/13/2010 9:20:57 AMAFAIL
Provide exit discharge lighting.
BLD10-01207 FIRE-Final Inspection9/10/20109/13/20109/13/2010 8:51:50 AMAPASS
life safety passed