Inspections for the day of: Tuesday, September 13, 2011.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-01568 FIRE-Final Inspection9/13/20119/13/20119/13/2011 5:02:18 PMPPART
Project related fire sprinkler permit final okay, fire life safety final pending adjustments to the fire alarm system.
BLD11-00416 FIRE-Conference9/13/20119/13/20119/13/2011 4:58:06 PMPDONE
Regarding fire alarm manual pull station locations.
BLD10-02330 FIRE-Final Inspection9/13/20119/13/20119/13/2011 4:56:53 PMPPASS
Fire life safety completed satisfactory.
BLD10-02862 FIRE-Alarm Testing9/13/20119/13/20119/13/2011 4:53:10 PMPPART
Fire alarm work passed field testing.
BLD11-02077 FIRE-Final Inspection9/12/20119/13/20119/13/2011 1:19:58 PMPPASS
Correction items per T. Cobbley verified for completion.
BLD11-01935 FIRE-Final Inspection9/12/20119/13/20119/13/2011 12:55:20 PMAPASS
Life safety pass pending approved hardware at the exterior vestibule door to be completed by building owner. Latch at the door knob from the tenant space disabled. Remainder of C/N items finished.
FIR11-00267 INSP-Final Inspection9/12/20119/13/20119/13/2011 12:50:58 PMAPASS
Field verified repair of one notification device at the 1st floor elevator lobby. Fire alarm permit final approved.
BLD11-01915 FIRE-Final Inspection9/13/20119/13/20119/13/2011 12:43:53 PMPPASS
Fire life safety inspection passed.
BLD11-00689 FIRE-Final Inspection9/12/20119/13/20119/13/2011 12:43:06 PMAPASS
C/N item verified for completion. Life safety finaled.