ELE19-01529
| Final | 9/6/2019 | 9/13/2019 | 9/13/2019 3:05:01 PM | P | PASS |
|
|
I am working on Friday but will be home after 3:00 PM Have worked out with Tom to meet Phone #: ###-#### Inspection requested via web by Ron MacCulloch....ok to final
|
ELE18-03803
| Electrical Rough-In | 9/9/2019 | 9/13/2019 | 9/13/2019 2:32:23 PM | P | PASS |
|
|
late pm // Russell Phone #: ###-####... heated tile floor ok to cover
|
ELE19-03029
| Final | 9/13/2019 | 9/13/2019 | 9/13/2019 2:10:49 PM | P | PASS |
|
|
Please call when you are in route. Phone #: ###-#### Inspection requested via web by Spencer McLean.... rigid cinduit verified for feed disconnect labelled, breakers installed, and wiring sized correctly discussed with contractor that equipment is hard wired and GFCI protection not needed-no recp
|
ELE19-03468
| Final | 9/13/2019 | 9/13/2019 | 9/13/2019 12:13:50 PM | P | PASS |
|
|
Ronald Smith Phone #: ###-#### Inspection requested via web by Dave Brueggemann.... permit for tile floor....electrical contractor taking responsibility for tile heat installed without rough in inspection...circuits holds and GFCI protection verified...ok to final
|
ELE19-02465
| Final | 9/13/2019 | 9/13/2019 | 9/13/2019 12:11:35 PM | P | PASS |
|
|
final permit...work complete of permit...permit for other work pulled...ok to final
|
MIS19-00293
| ELE-Final | 9/13/2019 | 9/13/2019 | 9/13/2019 11:47:06 AM | P | PASS |
|
|
ok to final permit pulled for heated tile floor..ELE19-03468
|
ELE19-03461
| Temporary Service | 9/13/2019 | 9/13/2019 | 9/13/2019 11:34:33 AM | P | PASS |
|
|
oh temp pole Phone #: ###-#### Inspection requested via web by Richard Gratiot... t/s o/h new ok
|
ELE19-03316
| Electrical Rough-In | 9/11/2019 | 9/13/2019 | 9/13/2019 10:52:46 AM | A | PASS |
|
|
We will be starting the install in the morning, so if you could do rough inspection late morning, we will be further along in the install. Phone #: ###-#### Inspection requested via web by Ashley Lanham... UL listing verified on material
discussed scope of job with onsite journeyman..will be backfeeding from subpanel-electrician will do load calc on subpanel for house, verify sub feed SER is rated to carry 125% of load, and electrician is required to be at FINAL to verify information.
|
ELE19-03433
| Electrical Rough-In | 9/12/2019 | 9/13/2019 | 9/13/2019 10:15:15 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Patrick Paz...rough ok to cover
|
ELE19-02285
| Final | 9/11/2019 | 9/13/2019 | 9/13/2019 9:46:01 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Barbara Szurgot...ok to final
|
ELE19-02006
| Electrical Rough-In | 9/12/2019 | 9/13/2019 | 9/13/2019 9:16:43 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton... front desk reception outlets and LV...access to junction boxes in wall at first 2 desks shall be accessible-verify at final...ok to cover
|
ELE19-03457
| Rough-In Permanent Service | 9/12/2019 | 9/13/2019 | 9/13/2019 8:45:13 AM | A | PASS |
|
|
Please contact when done Phone #: ###-#### Inspection requested via web by Thomas wilson...p/s u/g new ok
|
ELE17-03213
| DOC - Permit Expired | 9/13/2019 | 9/13/2019 | 9/13/2019 8:31:02 AM | A | PASS |
|
|
no work done...verified no activity in 180 days
|
ELE19-00955
| Final | 9/13/2019 | 9/13/2019 | 9/13/2019 8:16:12 AM | A | PASS |
|
|
We thought this final inspection was to be completed at the same time of the permanent service inspection as we were done with the project
Gate Code 1223 Any issues gaining access - call ###-#### Phone #: ###-#### Inspection requested via web by JENNY EMEL...
service shall have meter installed before final can be given
job complete...meter installed...ok to final
|
ELE17-01002
| ELE-Request for Extension | 9/13/2019 | 9/13/2019 | 9/13/2019 7:28:43 AM | A | PASS |
|
|
still under construction
|
ELE17-01002
| ELE-Aging Inspection | 9/13/2019 | 9/13/2019 | 9/13/2019 7:28:16 AM | | PASS |
|
|
permit extended
|