FIR04-00724
| INSP-Final Inspection | 9/14/2005 | 9/15/2005 | 9/16/2005 3:08:58 PM | A | PART |
|
|
Okay for final, however, the main control valves are shut at this time.
|
FIR05-00265
| INSP-Sprinkler Rough-in | 9/14/2005 | 9/15/2005 | 9/16/2005 8:59:36 AM | P | PART |
|
|
First floor lower office sprinkler rough-in is good for cover, also discussed uprights above drop ceiling at second level and garage door coverage in the warehouse area.
|
FIR05-00464
| INSP-Sprinkler Rough-in/Hydro | 9/14/2005 | 9/15/2005 | 9/15/2005 5:05:44 PM | A | PART |
|
|
UG hydrostatic test passed inspection, UG flushing performed after test was satisfactory.
|
BLD05-01757
| FIRE-Final Inspection | 9/15/2005 | 9/15/2005 | 9/15/2005 4:34:28 PM | P | PASS |
|
|
Items on correction notice have been completed, life safety finaled.
|
BLD05-01345
| FIRE-Conference | 9/15/2005 | 9/15/2005 | 9/15/2005 4:08:17 PM | P | DONE |
|
|
On site discussion with contractor regarding the proper location for duct smoke detectors.
|
FIR05-00190
| INSP-Sprinkler Rough-in/Hydro | 9/15/2005 | 9/15/2005 | 9/15/2005 3:26:49 PM | P | CANC |
|
|
No time for this inspection today, have rescheduled with contractor for friday am 9/16.
|
FIR05-00550
| INSP-Alarm Testing | 9/15/2005 | 9/15/2005 | 9/15/2005 3:24:59 PM | P | PASS |
|
|
Fire alarm passed inspection.
|
FIR05-00297
| INSP-Sprinkler Rough-in/Hydro | 9/15/2005 | 9/15/2005 | 9/15/2005 2:22:10 PM | P | CANC |
|
|
Inspection has been rescheduled for friday am 9/16/05.
|
FIR05-00297
| INSP-Supply line flush | 9/15/2005 | 9/15/2005 | 9/15/2005 2:19:58 PM | P | PART |
|
|
UG fire supply line flush is satisfactory.
|
FIR05-00335
| INSP-Alarm Testing | 9/15/2005 | 9/15/2005 | 9/15/2005 1:18:41 PM | P | PASS |
|
|
This permit has already been finaled on 7/1/05. Fire alarm permit finaled.
|
FIR05-00472
| INSP-Final Inspection | 9/15/2005 | 9/15/2005 | 9/15/2005 11:55:57 AM | P | FAIL |
|
|
Outside bells at both risers failed to function, duct smoke detectors tested okay, need record of signal verification at next inspection, still need sd cut sheet.
|
FIR05-00400
| INSP-Sprinkler Rough-in/Hydro | 9/14/2005 | 9/15/2005 | 9/15/2005 11:52:27 AM | A | FAIL |
|
|
Bushings are not allowed in this application at the fittings on the north side grid main see NFPA 13 6.4.6.1, provide seismic clearance for the 2" and 3" mains where they pass through the masonry wall, upright heads at the south attic are over 15' apart, inspectors test orfice is not correctly sized, provide approved plans at next inspection, provide relief valve for gridded system at riser.
|