FIR14-00070
| INSP-Sprinkler Rough-in | 9/12/2014 | 9/15/2014 | 9/15/2014 4:49:40 PM | P | PART |
|
|
UG fire supply line including the PIV and ductile riser okay for bury provided a plan modification is done to reflect changes in pipe route, added 45 and 90, and relocated riser room.
|
FIR14-00071
| INSP-Sprinkler Rough-in | 9/12/2014 | 9/15/2014 | 9/15/2014 4:45:33 PM | P | PART |
|
|
Revise thrust blocking at the 90 upstream of the ductile riser prior to cover.
|
FIR14-00556
| INSP-Sprinkler Rough-in | 9/12/2014 | 9/15/2014 | 9/15/2014 4:43:27 PM | P | PART |
|
|
UG fire supply line approved for cover.
|
FIR14-00554
| INSP-Sprinkler Rough-in | 9/12/2014 | 9/15/2014 | 9/15/2014 4:42:41 PM | P | FAIL |
|
|
UG work has been buried prior to inspection for cover.
|
FIR14-00432
| INSP-Final Inspection | 9/12/2014 | 9/15/2014 | 9/15/2014 4:41:30 PM | P | NR |
|
|
Communication fail at the panel.
|
BLD14-01237
| FIRE-Final Inspection | 9/15/2014 | 9/15/2014 | 9/15/2014 4:40:28 PM | P | NR |
|
|
Project related fire alarm and sprinkler permit finals pending.
|
FIR14-00442
| INSP-Final Inspection | 9/12/2014 | 9/15/2014 | 9/15/2014 4:39:02 PM | P | NR |
|
|
Incomplete due to project finishes.
|
BLD14-01761
| FIRE-Final Inspection | 9/12/2014 | 9/15/2014 | 9/15/2014 2:52:49 PM | P | PASS |
|
|
Verified C/N items on site.
|
BLD14-01951
| FIRE-Final Inspection | 9/15/2014 | 9/15/2014 | 9/15/2014 11:55:05 AM | P | PASS |
|
|
Fire life safety finaled.
|
BLD14-00650
| FIRE-Final Inspection | 9/12/2014 | 9/15/2014 | 9/15/2014 11:54:14 AM | A | FAIL |
|
|
Items noted include; reverse door hardware at the NW storage closet, extension cords are not to be used as a substitute for permanent power to appliances, repair gap at rated door to the second exit, threshold and overhead clearance at the exit doors from the assembly area are not compliant (missing ramp), post max occupancy sign per review note #9, sutie address does not match permit documents.
|
BLD14-01303
| FIRE-Final Inspection | 9/13/2014 | 9/15/2014 | 9/15/2014 11:02:46 AM | A | PASS |
|
|
Scope of work completed. Life safety inspection passed.
|
FIR14-00632
| INSP-Sprinkler Rough-in | 9/12/2014 | 9/15/2014 | 9/15/2014 11:01:53 AM | A | PART |
|
|
Overhead work at the elevator lobby sheetrock ceiling approved for cover.
|