ELE16-01521
| Electrical Rough-In | 9/15/2016 | 9/15/2016 | 9/15/2016 3:08:41 PM | P | PASS |
|
|
Floor heat in master bath Phone #: ###-#### Inspection requested via web by Eric Brown Floor heat only ok to cover
|
ELE16-02268
| Electrical Rough-In | 9/15/2016 | 9/15/2016 | 9/15/2016 2:36:17 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Celinda Winters Interior walls only ok to cover
|
ELE16-00662
| Electrical Rough-In | 9/15/2016 | 9/15/2016 | 9/15/2016 12:40:04 PM | P | PASS |
|
|
Partial rough in on wall 3.1 between grid lines H and M. Phone #: ###-#### Inspection requested via web by Debby Pierce ok to cover
|
ELE16-02993
| Electrical Rough-In | 9/14/2016 | 9/15/2016 | 9/15/2016 12:23:02 PM | P | PASS |
|
|
We need a Ufer inspection. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker ufer ok to cover
|
ELE16-02997
| Electrical Rough-In | 9/15/2016 | 9/15/2016 | 9/15/2016 12:23:02 PM | P | PASS |
|
|
Contact is Rene Ramakers. This is an underground inspection for the west duct bank related to B51 FAB. Phone #: ###-#### Inspection requested via web by Scott Campbell West high voltage duct bank ok to cover
|
ELE16-02049
| Conference | 9/12/2016 | 9/15/2016 | 9/15/2016 12:23:01 PM | A | DONE |
|
|
Meet at 17C lobby with Paul Cook. Discuss Micron inspections and return Green contractor badge. Phone #: ###-#### Inspection requested via web by Paul Cook Talked about Blanket permits and inspection procedures
|
ELE16-02856
| Permanent Service | 9/15/2016 | 9/15/2016 | 9/15/2016 10:34:02 AM | P | PASS |
|
|
any time after 10:00 am if posible Phone #: ###-#### Inspection requested via web by Glenn Bevan p/s o/h rec ok
|
ELE16-02856
| Temporary Service | 9/14/2016 | 9/15/2016 | 9/15/2016 10:09:44 AM | A | CANC |
|
|
any time after 10:00 am if posible Phone #: ###-#### Inspection requested via web by Glenn Bevan needed conference
|
ELE16-02898
| Rough-In Permanent Service | 9/14/2016 | 9/15/2016 | 9/15/2016 9:46:02 AM | A | FAIL |
|
|
electrical rough in, new construction Phone #: ###-#### Inspection requested via web by David Nelson 314.16 B Box fill. 2 gang by front door Calculated at 50 in a 43 box
|
ELE16-02536
| Final | 9/14/2016 | 9/15/2016 | 9/15/2016 9:18:23 AM | A | PASS |
|
|
please call prior to arrival for access information. Phone #: ###-#### Inspection requested via web by Patrick Paz Final ok
|
ELE16-00753
| Final | 9/14/2016 | 9/15/2016 | 9/15/2016 9:03:11 AM | A | PASS |
|
|
final for unit #101 Cottage A3 Phone #: ###-#### Inspection requested via web by Tracy Robertson final ok
|
ELE16-01977
| Final | 9/13/2016 | 9/15/2016 | 9/15/2016 8:53:37 AM | A | CANC |
|
|
Call when in route; check in with front desk. Phone #: ###-#### Inspection requested via web by Steve McCloy Needed rough in
|
ELE16-01977
| Electrical Rough-In | 9/15/2016 | 9/15/2016 | 9/15/2016 8:53:36 AM | P | PASS |
|
|
Call when in route; check in with front desk. Phone #: ###-#### Inspection requested via web by Steve McCloy Ceiling only ok to cover
|