Inspections for the day of: Monday, September 16, 2002.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-02399 BLD-Conference9/13/20029/16/20029/16/2002 12:00:00 AMADONE
Scheduled by a contractor via Hello! on 09/13/2002 at 11:44:13. Contact: ###-####. need to have the permit rewriten to show what areas are to be left unfinshed 9/16/2002 12:06:42 PM
BLD02-01916 BLD-Final9/13/20029/16/20029/16/2002 12:00:00 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung\ OFFICES 100-184 this was the only inspection done on this project 9/16/2002 12:05:17 PM
BLD02-02023 BLD-Footing9/16/20029/16/20029/16/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 09/16/2002 at 05:55:57. Contact: ###-####. ground under footing soft and wet areas over two ft thick need soils engineer or let ground dry out if it will 9/16/2002 10:41:30 AM
BLD02-01975 BLD-Foundation9/16/20029/16/20029/16/2002 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 09/16/2002 at 08:15:13. Contact: ###-####. all of the rebar is in forms about 45% complete 9/16/2002 4:35:22 PM
BLD02-02219 BLD-Final9/16/20029/16/20029/16/2002 12:00:00 AMPPASS
ROOF ###-#### JENNIFER this was the only inspection done on this project 9/16/2002 4:35:58 PM
MEC02-00628 Final9/13/20029/16/20029/16/2002 12:00:00 AMPPASS
###-#### OR ###-#### NEED TO CALL FIRST 9/16/2002 2:53:03 PM
BLD02-01650 BLD-Final9/12/20029/16/20029/16/2002 12:00:00 AMPFAIL
jana; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs to tape sheetrock joints in garage 9/16/2002 4:34:38 PM