PLM96-01931
| INSP - Final | 9/16/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | A | PASS |
|
|
09/17/96 352 - HE CALLED YOU ABOUT THIS AND MADE ARRANGEMENTS rp requires certification cap future drain openings
|
PLM96-02407
| INSP - Plumbing Rough-in | 9/16/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | A | PASS |
|
|
09/17/96 352 -
|
PLM96-02751
| INSP - Plumbing Rough-in | 9/16/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | A | PASS |
|
|
09/17/96 352 - 2 W/C 2 LAV 2 TUB/SHOWER 2 SINK 2 W/H 2 W/B FOR COMBO OF
|
PLM96-02754
| INSP - Sprinkler & Backflow | 9/16/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | A | PASS |
|
|
09/17/96 352 -
|
PLM96-02758
| INSP - Sewer line FINAL | 9/16/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | A | PASS |
|
|
09/17/96 352 - READY AT 10:30/ I TOLD HIM IF YOU COULDN'T DO IT BETWEEN 10:30 AND 12:00 YOU WOULD DO IT LUNCH. AJB
|
PLM96-02742
| INSP - Sewer/Water lines-FINAL | 9/16/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | A | PASS |
|
|
09/17/96 352 -
|
PLM96-02742
| INSP - Sewer/Water lines-FINAL | 9/17/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | A | PASS |
|
|
09/17/96 352 -
|
PLM96-02745
| INSP - Ground work | 9/17/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | P | PASS |
|
|
09/17/96 352 - REINSPECTION
|
PLM96-02761
| INSP - Sewer and Water lines | 9/17/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | P | PASS |
|
|
09/17/96 352 -
|
PLM96-02762
| INSP - Final | 9/17/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | P | NR |
|
|
09/17/96 352 -
|
PLM96-02649
| INSP - Sewer and Water lines | 9/17/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | P | PASS |
|
|
09/17/96 352 -
|
PLM96-02368
| INSP - Plumbing Rough-in | 9/17/1996 | 9/17/1996 | 9/17/1996 12:00:00 AM | P | PASS |
|
|
09/17/96 352 -
|