Inspections for the day of: Friday, September 17, 1999.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJoe Tawney
TitleFIRE INSPECTOR
Phone #340-1295
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-01344 FIRE-Final Inspection9/14/19999/17/19999/17/1999 12:00:00 AMPFAIL
REINSP - C/N NOT ONSITE - NEEDS TO BE RESCHEDULED
BLD99-00569 FIRE-Final Inspection9/16/19999/17/19999/17/1999 12:00:00 AMPPASS
REINSP OK FOR CERT OF COMPLETION
BLD99-01237 FIRE-Final Inspection9/16/19999/17/19999/17/1999 12:00:00 AMPCANC
Scheduled by a contractor via Hello! on 09/16/1999 at 17:44:05. Contact: ###-####. was sent to wrong inspector
BLD99-02207 FIRE-Final Inspection9/17/19999/17/19999/17/1999 12:00:00 AMPPART
OK FOR TEMP OCCUPANCY
MIS99-00158 FIR-Final9/17/19999/17/19999/17/1999 12:00:00 AMPPASS
OK FOR OCCUPANCY; MOVE FIRE EXT FROM CLOSET TO CORRIDOR
BLD99-00928 FIRE-Sprinkler Rough-in9/17/19999/17/19999/17/1999 12:00:00 AMPPART
OK ON SPRINKLER R/I