BLD13-01238
| BLD-Framing/Rough-in | 9/17/2013 | 9/17/2013 | 9/17/2013 4:41:57 PM | P | NR |
|
|
Matt Phone #: ###-####. Need mechanical rough in inspection. Provide additional approved plan mods and all special inspection reports.
|
ESC13-00339
| BMP Violation | 9/17/2013 | 9/17/2013 | 9/17/2013 4:40:56 PM | P | FAIL |
|
|
Repost ESC permit sign. Sweep all hard surfaces of silts. Perform general site cleanup. SWPPP not on site, proveide SWPPP with ESC plan. Construction site enterance needs to be serviced. Per owner they are going to place concrete at enterance and begin parking lot prep. RP was notified via verbal c/n.
|
BLD13-02288
| BLD-Framing/Rough-in | 9/16/2013 | 9/17/2013 | 9/17/2013 4:32:08 PM | P | FAIL |
|
|
Sysco Phone #: ###-####. Gable end truss requires continous bearing. Provide bearing or engineered fix from truss co.
|
BLD13-02480
| BLD-Final | 9/17/2013 | 9/17/2013 | 9/17/2013 3:51:38 PM | P | PASS |
|
|
Hi Mike please give me a call about 15 min before and I will meet you at the site Thanks Dan Phone #: ###-#### >> Inspection requested via web by Dan Elser
|
BLD13-02480
| DOC - Permit Finaled | 9/17/2013 | 9/17/2013 | 9/17/2013 3:51:27 PM | P | PASS |
|
|
|
BLD13-01521
| BLD-Final | 9/17/2013 | 9/17/2013 | 9/17/2013 3:40:15 PM | P | PASS |
|
|
AJ Phone #: ###-####
|
BLD13-01521
| DOC - Permit Finaled | 9/17/2013 | 9/17/2013 | 9/17/2013 3:40:03 PM | P | PASS |
|
|
|
BLD12-00382
| BLD-Final | 9/17/2013 | 9/17/2013 | 9/17/2013 2:55:59 PM | P | PART |
|
|
Mike Phone #: ###-####. sales tower issues resolved. ok to occupy sales tower and scion portion only.
|
ESC13-00654
| Random Inspection | 9/17/2013 | 9/17/2013 | 9/17/2013 2:39:51 PM | P | PASS |
|
|
|
BLD13-01808
| BLD-Framing/Rough-in | 9/17/2013 | 9/17/2013 | 9/17/2013 2:38:58 PM | P | PASS |
|
|
1st floor shear inspection please-Paul Phone #: ###-####. 1st. floor exteior wall bracing only ok.
|
ESC13-00561
| Site Preparation | 9/17/2013 | 9/17/2013 | 9/17/2013 1:40:53 PM | P | PASS |
|
|
charles Phone #: ###-####
|
BLD12-03333
| BLD-Final | 9/17/2013 | 9/17/2013 | 9/17/2013 12:39:22 PM | P | CANC |
|
|
rocko Phone #: ###-####. Cancelled by contractor via phone call.
|
BLD13-01626
| BLD-Energy code compliance | 9/16/2013 | 9/17/2013 | 9/17/2013 10:47:29 AM | A | PASS |
|
|
Brett Phone #: ###-####
|
BLD13-01832
| BLD-Footing | 9/16/2013 | 9/17/2013 | 9/17/2013 10:24:15 AM | A | PASS |
|
|
dane Phone #: ###-####
|
ESC13-00747
| Site Preparation | 9/16/2013 | 9/17/2013 | 9/17/2013 9:08:40 AM | A | PART |
|
|
duncan Phone #: ###-####. Construction enterance established, ESC permit sign has been posted with SWPPP at construction enterance. BMP's installed. Noted that waddles do not overlap at ends. SPoke to RP and idaho sand and gravel. They will check with Syman on install and correct if needed. Earth moving operations have begun.
|