FIR18-00632
| INSP-Sprinkler Rough-in | 9/14/2018 | 9/17/2018 | 9/18/2018 12:00:00 AM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus
Rough in ok. Insulation compatibility with CPVC to be verified.
_____________
Compatibility is verified. See attached document. 9/18/2018 TRF
|
FIR18-00680
| INSP-Sprinkler Rough-in/Hydro | 9/17/2018 | 9/17/2018 | 9/18/2018 12:00:00 AM | P | PASS |
|
|
Underground rough/hydro. Call Anthony with a time, will be ready this morning Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
_____________
Udg installation appeard to be adequate.
One hydro held fine, no loss.
The second hydro was low when I arrived. The contractor showed up and fixed a leak where the guage was connected. When I arrived the second time the UDG appeared to be holding pressure. I saw no visible leakeage.
|
NAF18-00108
| INSP-Final | 9/17/2018 | 9/17/2018 | 9/17/2018 12:00:00 AM | P | CANC |
|
|
Call prior to going Phone #: 2084125969 >> Inspection requested via mobile web by John Wood.
Inspection was requested by the building owner. Contractors were not present so inspection was canceled. Contractors are to call in for a new inspection date and be present.
|
FIR18-00632
| INSP-Sprinkler Rough-in | 9/14/2018 | 9/17/2018 | 9/14/2018 10:37:30 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|