PLM4046647
| INSP - Final | 9/15/1995 | 9/18/1995 | 9/18/1995 12:00:00 AM | A | PASS |
|
|
09/15/95 330 - 1-wc,2-lav,1-tub,1-si,1-wb,1-wh
|
PLM95-00986
| INSP - Ground Work/Sewer/Water | 9/15/1995 | 9/18/1995 | 9/18/1995 12:00:00 AM | A | FAIL |
|
|
09/15/95 330 - test all piping, remove all ground floor fixtures from ba
|
PLM95-00596
| INSP - Final | 9/18/1995 | 9/18/1995 | 9/18/1995 12:00:00 AM | P | PASS |
|
|
09/18/95 330 - 2-wc,2-lav,1-tub,1-sh,1-si,1-wb,1-wh,
|
PLM95-00651
| INSP - Plumbing Rough-in | 9/18/1995 | 9/18/1995 | 9/18/1995 12:00:00 AM | P | NR |
|
|
09/18/95 330 - 4 w/c 5 basin 3 tub 1 shower 2 sinks 1 w/b 1 w/h not ready, no test, correct fixture counrt- - - - 4-wc, 6-lav,3-tub,2-sh,2-si,1-wb,1-wh, of these 1-
|
PLM95-00655
| INSP - Water lines | 9/18/1995 | 9/18/1995 | 9/18/1995 12:00:00 AM | P | PASS |
|
|
09/18/95 330 - bldg 17c fab 1 next 100' north ok ì
|