ELE02-02888
| Rough-In Permanent Service | 9/17/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | A | PASS |
|
|
###-#### ok cover ri p/s u/g n ok 9/18/2002 9:47:53 AM
|
ELE02-02648
| Permanent Service | 9/17/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 09/17/2002 at 15:53:16. Contact: ###-####. p/s u/g n ok 9/18/2002 9:56:20 AM
|
ELE02-02896
| Final | 9/17/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | A | PASS |
|
|
Phone #: ###-#### Internet Inspection Request from: Dana Moyer ok final survey lable panal 9/18/2002 10:44:09 AM
|
ELE02-02144
| Final | 9/17/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 09/17/2002 at 17:17:16. Contact: ###-####. ok 2 disconnects grounding bonding--- conduit not strapped they recall after strapping completed 9/18/2002 10:50:42 AM
|
ELE02-02377
| Final | 9/17/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | A | PASS |
|
|
###-#### access code 1103 ok final 9/18/2002 10:11:36 AM
|
ELE02-02667
| Final | 9/17/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/17/2002 at 13:04:51. Contact: ###-####. ok final 9/18/2002 12:29:58 PM
|
ELE02-01133
| Final | 9/17/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | P | PASS |
|
|
###-#### ok final 9/18/2002 3:14:41 PM
|
ELE02-02854
| Permanent Service | 9/18/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | P | CANC |
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung wrong inspection 9/18/2002 1:26:27 PM
|
ELE02-02259
| Electrical Rough-In | 9/18/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | P | FAIL |
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung needs 20ft or more of clean area between footing & foundation for u-fer ground 9/18/2002 1:13:57 PM
|
ELE02-02854
| Final | 9/18/2002 | 9/18/2002 | 9/18/2002 12:00:00 AM | P | PASS |
|
|
PER MIKE ok final 9/18/2002 1:28:05 PM
|