Inspections for the day of: Thursday, September 18, 2008.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC08-00179 General Inspection9/18/20089/18/20089/18/2008 3:36:12 PMPFAIL
Vebal notice to the RP.
1. Need to install a sediment barrier on the north west side of project where the grade is sloping towards the parcel next to them.
2. Install perimeter protection surrounding the the stockpile at the east end of project.
3. Clean all storm drain inlets in the project area.
4. Need secondary protection on D.I. to the south of the stock pile or block off the D.I. .
5. Clean up all hardsurface of sediment debris on and offo of project area.
Will re-inspect on 9/19/08 in the PM.
CAS
ESC08-00491 General Inspection9/18/20089/18/20089/18/2008 3:31:04 PMPFAIL
Need to install proper construction entrances for project access.
Will be meeting with the RP on 9/19/08 to do a site overview of the project.
ESC08-00625 Site Final9/18/20089/18/20089/18/2008 2:47:01 PMPPASS
ESC06-00425 Site Final9/18/20089/18/20089/18/2008 9:25:01 AMAPASS
ESC06-00425 Site Final9/18/20089/18/20089/18/2008 9:03:22 AMAPASS
ESC08-00501 General Inspection9/18/20089/18/20089/18/2008 8:59:04 AM PASS
ESC05-02011 Site Final9/17/20089/18/20089/17/2008 3:18:19 PMAPASS
ESC05-01825 Site Final9/17/20089/18/20089/17/2008 3:18:04 PMAPASS
ESC05-01826 Site Final9/17/20089/18/20089/17/2008 3:16:36 PMAPASS
ESC05-01830 Site Final9/17/20089/18/20089/17/2008 3:16:09 PMAPASS
ESC05-01819 Site Final9/17/20089/18/20089/17/2008 3:15:48 PMAPASS
ESC05-01828 Site Final9/17/20089/18/20089/17/2008 3:15:25 PMAPASS
ESC05-01829 Site Final9/17/20089/18/20089/17/2008 3:14:47 PMAPASS