BLD96-02800
| INSP - Conference | 9/19/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | A | PASS |
|
|
MET W/ NEW SPEC INSP(W/MTI)...PERRY BRIAN. DISCUSSED NONCONFORMING INSP REPORTS; MUST BE COMPILED AND ADDRESSED BY ENG.
|
BLD96-02800
| INSP - Footings | 9/19/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PART |
|
|
09/19/97 340 - poured 14 yards 9/18/97 will call monday and let you know poured saturday. for interior and exterior. spec. inspector on job site.
|
BLD97-00044
| INSP - Carpentry | 9/18/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PART |
|
|
09/19/97 340 -
|
BLD97-00401
| INSP - Carpentry | 9/18/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PART |
|
|
09/19/97 340 - RE FINAL FOR #6
|
BLD97-00401
| INSP - Carpentry | 9/18/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PART |
|
|
09/19/97 340 -
|
BLD97-00494
| INSP - Carpentry | 9/18/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PART |
|
|
09/19/97 340 - W/JULIO, K2
|
BLD97-02079
| INSP - Carpentry | 9/18/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PASS |
|
|
09/19/97 340 - PER FINAL, looks ok, call for frame insp when ready
|
BLD97-02082
| INSP - Carpentry | 9/18/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PASS |
|
|
09/19/97 340 - PER FINAL
|
MEC97-02313
| INSP - Rough-in & Gas Pressure | 9/19/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | PART |
|
|
09/19/97 340 - 4 basic and fireplace; left c/n, gas test ok
|
MEC97-02561
| INSP - Rough-in & Gas Pressure | 9/19/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | NR |
|
|
09/19/97 340 - gave to 408
|
MEC97-02568
| INSP - Gas log/ Fireplace | 9/19/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | NR |
|
|
09/19/97 340 - nr, gave to 408
|
MEC97-02573
| INSP - Gas pressure test | 9/19/1997 | 9/19/1997 | 9/19/1997 12:00:00 AM | P | NR |
|
|
09/19/97 340 - not in city???
|