FIR03-00062
| INSP-Final Inspection | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | FAIL |
|
|
Hvac units did not shut down upon alarm, provide the NFPA 72 record of completion forms 9/2/2003 10:36:28 AM
|
BLD02-02471
| FIRE-Sprinkler Rough-in | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | FAIL |
|
|
No items on the correction notice have been corrected 9/2/2003 10:37:37 AM
|
BLD02-02471
| FIRE-Final Inspection | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | FAIL |
|
|
No items on the correction notice have been corrected 9/2/2003 10:38:57 AM
|
BLD02-02473
| FIRE-Final Inspection | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | FAIL |
|
|
No items on the correction notice have been corrected 9/2/2003 10:39:03 AM
|
BLD02-02473
| FIRE-Sprinkler Rough-in | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | FAIL |
|
|
No items on the correction notice have been corrected 9/2/2003 10:39:08 AM
|
BLD02-02474
| FIRE-Sprinkler Rough-in | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | FAIL |
|
|
No items on the correction notice have been corrected 9/2/2003 10:39:47 AM
|
BLD02-02474
| FIRE-Final Inspection | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | FAIL |
|
|
No items on the correction notice have been corrected 9/2/2003 10:39:34 AM
|
BLD02-00311
| FIRE-Conference | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | DONE |
|
|
jim ###-#### Went over alarm audibility issues with the engineer. They do have to meet all requirements of the code. The sprinkler contractor can use the 2002 NFPA 13 earthquaking requirements for the installations on this project 9/2/2003 9:45:25 AM
|
BLD02-00311
| FIRE-Conference | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | A | DONE |
|
|
jim ###-#### Went over alarm audibility issues with the engineer. They do have to meet all requirements of the code. The sprinkler contractor can use the 2002 NFPA 13 earthquaking requirements for the installations on this project 9/2/2003 9:45:25 AM
|
BLD03-00722
| FIRE-Final Inspection | 8/29/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | P | FAIL |
|
|
Provide emergency shutoff signage in locations per conversation and provide a fire extinguisher in the shelter 9/2/2003 1:43:43 PM
|
FIR03-00074
| INSP-Sprinkler Rough-in/Hydro | 8/28/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | P | PASS |
|
|
sprinkler rough-in is ok. Sprinkler piping is OK to cover 9/2/2003 3:51:56 PM
|
FIR03-00090
| INSP-Sprinkler Rough-in/Hydro | 9/2/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | P | PART |
|
|
RICK; Phone #: ###-#### Hydro test is OK 9/2/2003 3:46:27 PM
|
FIR03-00006
| INSP-Sprinkler Rough-in/Hydro | 9/2/2003 | 9/2/2003 | 9/2/2003 12:00:00 AM | P | PART |
|
|
provide as-builts to the city of boise showing the new hose vavle locations, provide EQ bracing on the 4" piping in the locations as discussed, provide signage for the stand pipe per review notes, provide verification that there is adequate clearance for hose hookup at the top north hose vavle with the fire dept. Hydro test is OK 9/2/2003 3:04:21 PM 9/2/2003 3:08:33 PM
|