BLD13-00694
| FIRE-Final Inspection | 8/13/2014 | 9/2/2014 | 9/2/2014 4:41:06 PM | P | PASS |
|
|
Life safety passed. Scope of work completed.
|
FIR14-00576
| INSP-Final Inspection | 9/2/2014 | 9/2/2014 | 9/2/2014 2:53:47 PM | P | PART |
|
|
Modifications to occupant notification appear complete per the scope of work. However, a manual pull station will be required adjacent to the new stairway exit door. Functional testing and permit final pending.
|
BLD14-02000
| FIRE-Final Inspection | 9/1/2014 | 9/2/2014 | 9/2/2014 2:50:42 PM | P | FAIL |
|
|
Items noted include; missing exit sign, remove locking hardware at the egress side from the second exit access door, install new 20 min door per plan at the new corridor east side, project related fire alarm and sprinkler permit finals pending corrections and finishes.
|
FIR14-00508
| INSP-Final Inspection | 9/2/2014 | 9/2/2014 | 9/2/2014 2:46:02 PM | P | PART |
|
|
Sprinkler final pending installation of field ceiling tile. Remainder of walkthrough passed.
|