Inspections for the day of: Wednesday, September 2, 2015.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR15-00395 INSP-Sprinkler Rough-in9/2/20159/2/20159/2/2015 2:50:28 PMPPART
Partial Piping for building installed, piping that is installed approved for cover, still needs tie in to water supply, will be scheduled for inspection at later date for completion of cover inspection.
FIR15-00397 INSP-Sprinkler Rough-in9/2/20159/2/20159/2/2015 2:49:31 PMPPART
Partial Piping for building installed, piping that is installed approved for cover, still needs tie in to water supply, will be scheduled for inspection at later date for completion of cover inspection.
FIR15-00396 INSP-Sprinkler Rough-in9/2/20159/2/20159/2/2015 2:48:22 PMPPART
Partial Piping for building installed, piping that is installed approved for cover, still needs tie in to water supply, will be scheduled for inspection at later date for completion of cover inspection.
FIR15-00595 INSP-Sprinkler Rough-in9/2/20159/2/20159/2/2015 12:52:00 PMPPASS
Underground supply line inspection passed/complete, approved for cover.
FIR15-00611 INSP-Sprinkler Rough-in9/1/20159/2/20159/2/2015 8:38:06 AMAPASS
Rough-in inspection passed/complete