ESC15-00076
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 4:47:04 PM | | PASS |
|
|
WIP at Ashville Commons. No trackout or fugitive dust, perimeter controls installed. Concrete washout for curb work and foundation has been contained onsite. See ESC14-01052 for full site permit. ESC15-00070 to ESC15-00083 are for the individual structures/four-plexes. No corrections issued.
|
ESC15-00075
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 4:46:28 PM | | PASS |
|
|
WIP at Ashville Commons. No trackout or fugitive dust, perimeter controls installed. Concrete washout for curb work and foundation has been contained onsite. See ESC14-01052 for full site permit. ESC15-00070 to ESC15-00083 are for the individual structures/four-plexes. No corrections issued.
|
ESC15-00074
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 4:46:12 PM | | PASS |
|
|
WIP at Ashville Commons. No trackout or fugitive dust, perimeter controls installed. Concrete washout for curb work and foundation has been contained onsite. See ESC14-01052 for full site permit. ESC15-00070 to ESC15-00083 are for the individual structures/four-plexes. No corrections issued.
|
ESC15-00073
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 4:45:56 PM | | PASS |
|
|
WIP at Ashville Commons. No trackout or fugitive dust, perimeter controls installed. Concrete washout for curb work and foundation has been contained onsite. See ESC14-01052 for full site permit. ESC15-00070 to ESC15-00083 are for the individual structures/four-plexes. No corrections issued.
|
ESC15-00072
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 4:45:40 PM | | PASS |
|
|
WIP at Ashville Commons. No trackout or fugitive dust, perimeter controls installed. Concrete washout for curb work and foundation has been contained onsite. See ESC14-01052 for full site permit. ESC15-00070 to ESC15-00083 are for the individual structures/four-plexes. No corrections issued.
|
ESC15-00071
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 4:45:02 PM | | PASS |
|
|
WIP at Ashville Commons. No trackout or fugitive dust, perimeter controls installed. Concrete washout for curb work and foundation has been contained onsite. See ESC14-01052 for full site permit. ESC15-00070 to ESC15-00083 are for the individual structures/four-plexes. No corrections issued.
|
ESC13-00924
| Random Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 3:36:28 PM | P | PASS |
|
|
All construction complete in Pine Tree Village. Open areas have been landscaped.
Need a final street sweeping to around recently finished area.
Drop inlet bags in completed areas have already been removed as requested.
|
ESC15-00499
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 3:18:10 PM | P | PASS |
|
|
WIP on Overland Del Taco. Frontage vegetation along Overland is preserved and access restricted. Construction traffic entering from sout. No fugitive dust, trackout, or discharges. Approved
|
ESC14-00961
| Random Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 2:41:17 PM | P | PASS |
|
|
WIP. Home remodel complete, front yard fenced and stabilized. Garage and driveway are in progress. Permit sign posted. No corrections issued.
|
ESC15-00200
| Aging Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 1:32:10 PM | | PASS |
|
|
WIP on overland Primary Care. No violations observed. Permit sign posted.
|
ESC15-00703
| Random Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 12:26:09 PM | P | PASS |
|
|
WIP on home addition. Permit sign posted. No sediment or discharges leaving site. No corrections.
|
ESC15-00132
| DOC - Permit Finaled | 9/2/2015 | 9/2/2015 | 9/2/2015 12:23:56 PM | P | PASS |
|
|
Work complete. No construction or disturbed area at site. BLD still open.
|
ESC15-00050
| Aging Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 12:13:25 PM | | PART |
|
|
Home complete, landscaped and occupied. ESC permit conditions satisfied. Will have Brighton pull all DI bags in Mill District Square once all construction is complete. The Square is over 75% complete.
|
ESC15-00050
| DOC - Permit Finaled | 9/2/2015 | 9/2/2015 | 9/2/2015 12:12:11 PM | P | PASS |
|
|
|
ESC14-00809
| General Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 12:04:00 PM | | PART |
|
|
DI bag in front of project is installed and was recently maintained. Permit sign is posted at driveway
Sediment trackout occuring onto Starview. Need to install a stabilized construction entrance and sediment control BMPs upslope. No discharges occuring.
Message left with Hard Rock Construction RP, will wait for call back for corrections. Tracking control inspection scheduled.
|
ESC15-00065
| Site Preparation | 9/1/2015 | 9/2/2015 | 9/2/2015 11:55:46 AM | A | PEND |
|
|
note: not a site prep inspection, data entry error
Corrective actions in progress to fix grading. Vegetative perimeter buffer has remained undisturbed. No discharges or sediment runoff at time of inspection
|
ESC15-01072
| Site Preparation | 9/2/2015 | 9/2/2015 | 9/2/2015 11:29:37 AM | P | PASS |
|
|
WIP setting up perimeter fencing for the staging area within the culdesac in park near Broadway. No boring work has commenced. Will check in with RP during operations. No stormwater pollution issues observed.
|
ESC15-00132
| Aging Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 9:33:23 AM | | PASS |
|
|
|
ESC14-00592
| Aging Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 9:02:13 AM | | PASS |
|
|
WIP at the District. No trackout, perimeter controls in good condition. Water truck on site doing rounds to control fugitive dust. No dewatering currently, however the irrigation ditch is passing through site and discharging into Logger's Creek. Work is being conducted with care around the ditch as not to stir up or dump sediment into the irrigation water. At time of inspection there was no significant plume observed.
No corrections at this time.
|
ESC14-00591
| Aging Inspection | 9/2/2015 | 9/2/2015 | 9/2/2015 9:01:53 AM | | PASS |
|
|
WIP at the District. No trackout, perimeter controls in good condition. Water truck on site doing rounds to control fugitive dust. No dewatering currently, however the irrigation ditch is passing through site and discharging into Logger's Creek. Work is being conducted with care around the ditch as not to stir up or dump sediment into the irrigation water. At time of inspection there was no significant plume observed.
No corrections at this time.
|