PLM95-00732
| INSP - Final | 9/19/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | A | CANC |
|
|
09/20/95 347 -
|
PLM95-01009
| INSP - Sprinkler & Backflow | 9/19/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | A | CANC |
|
|
09/20/95 347 -
|
PLM95-01013
| INSP - Sewer and Water lines | 9/19/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | A | CANC |
|
|
09/20/95 347 -
|
PLM95-01013
| INSP - Sewer and Water lines | 9/19/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | A | CANC |
|
|
09/20/95 347 -
|
PLM95-01014
| INSP - Plumbing Rough-in | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | PASS |
|
|
09/20/95 347 - FIXTURE COUNT W/C 2 BASIN 2 TUB 2 SINK 1 WASHER 1 W/H 1
|
PLM95-01011
| INSP - Water softener | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | PASS |
|
|
09/20/95 347 -
|
PLM95-00749
| INSP - Final | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | PASS |
|
|
09/20/95 347 - fixture count w/c 2 basin 2 tub 2 sink 1 washer 1 w/h 1
|
PLM95-00851
| INSP - Plumbing Rough-in | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | PASS |
|
|
09/20/95 347 - after 1:00
|
PLM95-00852
| INSP - Ground work | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | PASS |
|
|
09/20/95 347 - after 1:00
|
PLM95-00946
| INSP - Sewer line | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | CANC |
|
|
09/20/95 347 -
|
PLM95-00989
| INSP - Ground work | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | PASS |
|
|
09/20/95 347 - APPROVED 9-19-95
|
PLM4042611
| INSP - Final | 9/20/1995 | 9/20/1995 | 9/20/1995 12:00:00 AM | P | PASS |
|
|
09/20/95 347 - This was an inspection that was schedule for Aug. 30th and there was never nothing done. thanks Rita !!!!!! TOUGH! ANOTICE WASLEFT ON THE FRONT WINDOW THAT WE COULD NOT GAIN ACCESS, MAYB
|