PLM99-02819
| Final | 9/17/1999 | 9/20/1999 | 9/22/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 09/17/1999 at 14:25:02. Contact: ###-####.done on the 22nd
|
PLM99-03217
| Final | 9/20/1999 | 9/20/1999 | 9/21/1999 12:00:00 AM | P | PASS |
|
|
|
PLM99-03206
| Final | 9/17/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | A | PART |
|
|
Partial need relief line
|
PLM99-03035
| Plumbing Rough-in | 9/20/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | A | PASS |
|
|
|
PLM99-03216
| Final | 9/20/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | P | FAIL |
|
|
###-####
|
PLM99-03217
| Final | 9/20/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | P | FAIL |
|
|
DAVE-- ###-#### WATER LINE ONLY
|
PLM99-02518
| Final | 9/20/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | P | FAIL |
|
|
mary-- ###-#### fn insp
|
PLM99-03220
| Plumbing Rough-in | 9/20/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/20/1999 at 11:06:35. Contact: . R/I ok
|
PLM99-02518
| Final | 9/20/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | P | PASS |
|
|
|
PLM99-03198
| Water and/or Sewer | 9/17/1999 | 9/20/1999 | 9/20/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/17/1999 at 17:48:19. Contact: ###-####.
|