Inspections for the day of: Wednesday, September 20, 2006.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Johnson
TitlePLM-INSPECTOR
Phone #794-9476
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM06-00535 PLM-Aging Inspection9/20/20069/20/20069/21/2006 9:07:38 AM PASS
PLM06-03194 Plumbing Rough-in9/20/20069/20/20069/20/2006 5:06:27 PMPPASS
caldwell plumbing; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
PLM06-01102 Plumbing Rough-in9/19/20069/20/20069/20/2006 4:20:46 PMPPASS
Scheduled by a contractor via Hello! on 9/19/2006 at 3:49:02 PM.
PLM06-03191 Groundwork9/19/20069/20/20069/20/2006 3:16:32 PMPPART
brittany; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley need to increse fs-1 in fire riser room to 4 inch as noted on approved set of plan,s need end of the line full size clean out installed on four inch trunk line
PLM06-03146 Plumbing Rough-in9/20/20069/20/20069/20/2006 3:10:42 PMPPASS
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
PLM06-02684 Water and/or Sewer9/20/20069/20/20069/20/2006 1:20:02 PMPPART
jim - ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley five more sewer line extension test ok
PLM06-03104 Plumbing Rough-in9/19/20069/20/20069/20/2006 11:19:07 AMANR
Phone #: ###-#### Internet Inspection Request from: raul castanon not ready contractor to recall when ready
PLM06-03189 Sprinkler (Final)9/19/20069/20/20069/20/2006 10:15:38 AMAPASS
george; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
PLM06-03063 Plumbing Rough-in9/19/20069/20/20069/20/2006 10:15:19 AMAPART
Please inspect parital A-wing underground tomorrow AM; Phone #: ###-#### Internet Inspection Request from: Carl Homola need to correct leak in Y at end of line clean out and retest
PLM06-03185 Sprinkler (Final)9/19/20069/20/20069/20/2006 9:19:41 AMAPASS
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
PLM06-01401 Final9/19/20069/20/20069/20/2006 8:56:14 AMAPART
joe - call prior to insp for info concerning unit 'B'; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley need double check tested and certified anchor all wall hydrant,s missing some strainers on shower,s in some unit,s called contractor will recall when ready
PLM06-02624 Plumbing Rough-in9/19/20069/20/20069/20/2006 8:12:55 AMAPASS
john - storm drain ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley storm drains test ok