FIR04-00490
| INSP-Final Inspection | 9/19/2007 | 9/20/2007 | 9/24/2007 9:43:00 AM | A | FAIL |
|
|
The DSW head installed appears to be the wrong temperature-verify exta high temp. is provided, the flow switch at the SW supply pipe is not connected, provide approved access hatch as described per fire code review notes.
|
FIR07-00614
| INSP-Final Inspection | 9/20/2007 | 9/20/2007 | 9/21/2007 1:46:15 PM | P | PASS |
|
|
Resubmittals verified for compliance, final fire sprinkler inspection passed.
|
FIR07-00772
| INSP-Sprinkler Rough-in | 9/19/2007 | 9/20/2007 | 9/21/2007 10:56:27 AM | A | PART |
|
|
Two existing standard response heads at the east corner need to be QR type matching the new heads installed in the same fire area, also missing hangers at five arm-overs to new pendent heads, see plans for annotations, rough-in approved for cover pending corrections.
|
BLD07-00625
| FIRE-Conference | 9/19/2007 | 9/20/2007 | 9/21/2007 10:27:40 AM | A | DONE |
|
|
On site conference regarding fire sprinkler coverage at a storage room below the entry stairway, also discussed fire alarm permit work.
|
FIR07-00344
| INSP-Sprinkler Rough-in | 9/20/2007 | 9/20/2007 | 9/20/2007 3:50:00 PM | P | PART |
|
|
Begin 24 hr. air testing of the two new dry systems at 42psi each @3:30 pm.
|
BLD07-01848
| FIRE-Final Inspection | 9/20/2007 | 9/20/2007 | 9/20/2007 3:45:53 PM | P | FAIL |
|
|
Need to final project related fire sprinkler permit prior to life safety final, missing ceiling tile, floor coverings, electrical junction boxes are open, project is not ready for final at this time.
|
BLD06-00740
| FIRE-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 2:57:54 PM | P | PASS |
|
|
Fire life safety finaled, c/n items are complete.
|
BLD07-00851
| FIRE-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 2:56:53 PM | P | PASS |
|
|
Required corrections are finished, fire life safety final inspection passed.
|
BLD06-00500
| FIRE-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 2:55:43 PM | P | PASS |
|
|
All noted items for correction have been completed, fire life safety inspection passed.
|
FIR06-00753
| INSP-Final Inspection | 9/20/2007 | 9/20/2007 | 9/20/2007 2:54:16 PM | P | PASS |
|
|
UG fire supply line permit finaled.
|
FIR07-00501
| INSP-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 2:53:04 PM | A | PASS |
|
|
Noted items at the previous inspection have been verified for completion, fire sprinkler permit finaled.
|
FIR06-00995
| INSP-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 2:02:39 PM | A | PASS |
|
|
Final inspection passed, supply line flushed, double check backflow to be certified today, one missing escutcheon installed and travel cap at the ssu at the riser removed while on site, also need to install a test orifice at the inspectors test connection.
|
FIR07-00619
| INSP-Sprinkler Rough-in/Hydro | 9/19/2007 | 9/20/2007 | 9/20/2007 1:51:32 PM | A | NR |
|
|
Permit work is not yet completed for inspection at this time.
|
FIR07-00718
| INSP-Sprinkler Rough-in/Hydro | 9/19/2007 | 9/20/2007 | 9/20/2007 1:49:56 PM | A | PART |
|
|
Overhead rough-in is acceptable, no access provided to a janitors room-will verifiy at next visit, noted a hydrostatic test for this portion of the building has been completed,
|
FIR07-00316
| INSP-Sprinkler Rough-in/Hydro | 9/19/2007 | 9/20/2007 | 9/20/2007 1:46:45 PM | A | PASS |
|
|
UG fire supply line passed hydrostatic testing.
|
FIR07-00620
| INSP-Sprinkler Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 1:41:27 PM | A | PART |
|
|
Remainder of the overhead rough-in is approved for cover as noted on stamped plan set.
|