BLD07-01061
| BLD-Foundation | 9/20/2007 | 9/20/2007 | 9/20/2007 5:59:53 PM | P | PASS |
|
|
pete Phone #: ###-####
|
BLD07-02433
| BLD-Framing/Rough-in | 9/20/2007 | 9/20/2007 | 9/20/2007 3:28:06 PM | P | FAIL |
|
|
james Phone #: ###-#### Complete airseal package, Fireblock mech shaft at ceiling level upatairs, Provide mech connection for 2x8 fur down in bedroom down stairs, no mech insp yet. c/n posted.
|
BLD07-01138
| BLD-Framing/Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 2:14:50 PM | P | PART |
|
|
gary Phone #: ###-####.. CMU wall, sw end top of wall, wip, installing verts.
|
BLD07-01589
| BLD-Foundation | 9/19/2007 | 9/20/2007 | 9/20/2007 11:12:12 AM | A | PASS |
|
|
phillip Phone #: ###-####
|
BLD07-01595
| BLD-Foundation | 9/19/2007 | 9/20/2007 | 9/20/2007 11:11:56 AM | A | PASS |
|
|
phillip Phone #: ###-####
|
BLD07-01596
| BLD-Foundation | 9/19/2007 | 9/20/2007 | 9/20/2007 11:11:38 AM | A | PASS |
|
|
phillip Phone #: ###-####
|
BLD07-01597
| BLD-Foundation | 9/19/2007 | 9/20/2007 | 9/20/2007 11:11:22 AM | A | PASS |
|
|
phillip Phone #: ###-####
|
BLD07-01600
| BLD-Foundation | 9/19/2007 | 9/20/2007 | 9/20/2007 11:10:59 AM | A | PASS |
|
|
phillip Phone #: ###-####
|
BLD07-01099
| BLD-Final | 9/19/2007 | 9/20/2007 | 9/20/2007 10:03:14 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 9/19/2007 at 6:19:10 PM. Contact: ###-####. Handrail mounted to low. c/n posted.
|
BLD07-01545
| BLD-Framing/Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 9:38:22 AM | A | PART |
|
|
Becky; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Needs to pull elec permit with city, also plumbing ri done prior to install of can lights, pex pipe is to close to lights, 12 inch clearance required as per conversation with Jim J. plumbing insp.
|
BLD07-01819
| BLD-Final | 9/19/2007 | 9/20/2007 | 9/20/2007 12:00:00 AM | A | CANC |
|
|
sunny Phone #: ###-####
|