FIR11-00501
| INSP-Final Inspection | 9/20/2011 | 9/20/2011 | 9/20/2011 5:29:21 PM | P | PASS |
|
|
Hood suppression permit finaled.
|
FIR11-00516
| INSP-Sprinkler Rough-in | 9/20/2011 | 9/20/2011 | 9/20/2011 5:28:37 PM | P | PART |
|
|
UG fire supply line including the IBR approved for bury.
|
FIR11-00355
| INSP-Sprinkler Rough-in | 9/20/2011 | 9/20/2011 | 9/20/2011 5:24:44 PM | P | PART |
|
|
Reinspection for the second floor classrooms and 1st floor RR completed. Okay for cover at rooms 203, 205 and 206 new addition- noted one missing seismic brace at room 203. Restrooms 1st floor east side also approved for cover.
|
FIR11-00439
| INSP-Sprinkler Rough-in/Hydro | 9/20/2011 | 9/20/2011 | 9/20/2011 2:42:28 PM | P | PART |
|
|
Overhead hydrostatic testing passed. Also verified relocated pendent heads at the second floor.
|
BLD11-01585
| FIRE-Conference | 9/20/2011 | 9/20/2011 | 9/20/2011 2:40:45 PM | P | DONE |
|
|
On site conference with tenant regarding fire life safety conditions for occupancy approval.
|
FIR11-00501
| INSP-Sprinkler Rough-in | 9/19/2011 | 9/20/2011 | 9/20/2011 2:35:15 PM | A | PART |
|
|
Hood suppression system operated correctly under test conditions.
|
BLD11-00973
| FIRE-Final Inspection | 9/19/2011 | 9/20/2011 | 9/20/2011 2:27:41 PM | A | PASS |
|
|
|
BLD11-01653
| FIRE-Final Inspection | 9/19/2011 | 9/20/2011 | 9/20/2011 2:26:59 PM | A | PASS |
|
|
Fire life safety inspection completed satisfactory.
|
FIR11-00387
| INSP-Final Inspection | 9/20/2011 | 9/20/2011 | 9/20/2011 2:25:41 PM | P | PASS |
|
|
Fire sprinkler work passed final walkthrough. Permit finaled.
|