FIR15-00727
| INSP-Final Inspection | 9/13/2016 | 9/20/2016 | 9/20/2016 2:36:38 PM | P | CANC |
|
|
Inspection request will be completed on 21SEPT2016, this inspection request cancelled and new inspection request coordinated with job site foreman.
|
FIR15-00561
| INSP-Sprinkler Rough-in | 9/13/2016 | 9/20/2016 | 9/20/2016 1:09:56 PM | P | DONE |
|
|
Fire pump start up complete.
|
FIR16-00322
| INSP-Sprinkler Rough-in | 9/19/2016 | 9/20/2016 | 9/20/2016 1:09:21 PM | P | PASS |
|
|
Tenting inspection for fire sprinkler piping in attic spaces on level 4 and level 3 complete. Overhead fire sprinkler piping/tenting on level 3 and 4 approved for cover.
|
FIR16-00088
| INSP-Sprinkler Rough-in | 9/19/2016 | 9/20/2016 | 9/20/2016 10:55:37 AM | A | PASS |
|
|
Rough to cover inspectio for overhead fire sprinkler piping on level 4 complete, overhead fire sprinkler piping on level 4 approved for cover. Informed job site superintendent to watch the insulation above metal channel, detail on fire sprinkler city approved drawings specifies how the insulation needs to be installed above the metal channel. Inspection for remaining overhead fire sprinkler piping located on level 3 complete, all overhead fire sprinkler piping located on level 3 approved for cover.
|
FIR15-00767
| INSP-Final Inspection | 9/15/2016 | 9/20/2016 | 9/20/2016 10:02:31 AM | A | CANC |
|
|
Inspection request was moved to this afternoon, due to scheduling issues for this afternoon this inspection request is cancelled and will be rescheduled for 10am on 21SEPT2016.
|
FIR15-00727
| INSP-Sprinkler Rough-in/Hydro | 9/13/2016 | 9/20/2016 | 9/13/2016 11:43:36 AM | P | CANC |
|
|
Please schedule this final inspection for Convention Center. If you have questions please call Mike Martin at ###-####. Thank you. Phone #: ###-#### >> Inspection requested via web by Kay Haney Inspection cancelled from web by: Kay Haney
|