FIR17-00533
| INSP-Final Inspection | 9/19/2017 | 9/20/2017 | 9/20/2017 2:19:59 PM | P | PASS |
|
|
Final fire sprinkler inspection for area of work passed/complete.
|
BLD17-00105
| FIRE-Final Inspection | 9/20/2017 | 9/20/2017 | 9/20/2017 12:25:06 PM | P | PART |
|
|
Partial final inspection complete for tenant space associated with this permit. As per signed TCO agreement, fire pump testing/commissioning is complete, tamper switch and flow switch testing is complete for levels 1 and 2 wet pipe fire sprinkler systems, tamper switch/pressure switch and high low air sensor testing complete for levels 1 and 2 dry pipe fire sprinkler systems, commercial hood fire suppression system inspection is complete (FIR permit for hood suppression system will remain in issued status until core and shell permits for building are complete and passed), fire sprinkler inspection complete for tenant space (FIR permit for fire sprinklers will remain in issued status until core and shell inspections are complete), fire alarm inspection complete for tenant space (FIR permit for fire alarms will remain in issued status until core and shell inspections are complete), fire extinguishers are in place with current inspection tags. Per note number 8 of the signed temporary occupancy plan no employees will be in the space except for the 2 owners and their executive chef until TCO is authorized.
|
FIR16-00383
| INSP-Alarm Testing | 9/18/2017 | 9/20/2017 | 9/20/2017 12:06:09 PM | A | PART |
|
|
Fire alarm testing complete for fire pump riser room/fire pump room dry systems (Parking levels 1 and 2 dry systems). All tampers and flow switches in fire pump room complete, fire pump monitoring complete, tampers and flows complete for levels 1 and 2 wet systems.
|
FIR16-00194
| INSP-Sprinkler Rough-in/Hydro | 9/18/2017 | 9/20/2017 | 9/20/2017 12:02:59 PM | A | PASS |
|
|
24 hour air test complete for levels 1 and 2 dry systems.
|
FIR16-00194
| INSP-Sprinkler Rough-in | 9/20/2017 | 9/20/2017 | 9/20/2017 12:02:16 PM | A | PART |
|
|
Fire pump start up/commissioning complete. All tamper switches and flow switches in fire pump room complete. Final inspection for tampers and flows on level 1 and 2 wet systems complete.
|
FIR16-00194
| INSP-Alarm Testing | 9/19/2017 | 9/20/2017 | 9/20/2017 12:00:14 PM | A | CANC |
|
|
Pump test at nine am. Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR16-00267
| INSP-Sprinkler Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 11:59:24 AM | A | PART |
|
|
Rough to cover inspection for trash shoots on levels 5 and 7 complete, approved for cover. Inspection for remaining overhead fire sprinkler piping on level 5 complete, level 5 approved for cover.
|
FIR17-00280
| INSP-Alarm Testing | 9/18/2017 | 9/20/2017 | 9/20/2017 11:53:04 AM | A | DONE |
|
|
Fire alarm testing complete for tenant space, interface between commercial hood fire suppression system complete. Fire alarm permit can be finaled for tenant space when core and shell fire alarm inspections are complete and passed
|
FIR17-00334
| INSP-Final Inspection | 9/19/2017 | 9/20/2017 | 9/20/2017 11:48:29 AM | A | PART |
|
|
Final commercial hood fire suppression system inspection complete, permit will remain in issued status until final inspections are complete for core and shell.
|
BLD17-00583
| FIRE-Conference | 9/20/2017 | 9/20/2017 | 9/20/2017 8:50:56 AM | A | DONE |
|
|
Noted that I spoke with the superintendent with Headwaters Construction (Chris Stanton, phone number ###-####) about a temporary standpipe being installed, note number 42 of the building permit fire code review gives the specifics of the temporary standpipe being required. Builiding is up to level 5 at the time of this entry with no temp standpipe in place.
|
FIR17-00267
| INSP-Sprinkler Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 8:46:10 AM | P | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping located above the pre-rock in the corridor on the level 2 complete, notated the city approved drawings with red ink area's approved for cover. Approved plans for inspections is located in the job shack. Noted that I spoke with the superintendent with Headwaters Construction (Chris Stanton, phone number ###-####) about a temporary standpipe being installed, note number 42 of the building permit fire code review gives the specifics of the temporary standpipe being required.
|
FIR17-00267
| INSP-Sprinkler Rough-in | 9/19/2017 | 9/20/2017 | 9/19/2017 3:03:16 PM | P | CANC |
|
|
Contact Perly Daniel ###-#### 30 min prior to RTC Insp. start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
FIR16-00194
| INSP-Sprinkler Rough-in/Hydro | 9/18/2017 | 9/20/2017 | 9/18/2017 2:16:16 PM | A | CANC |
|
|
Finish 24 hour air test on first floor dry system Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|