BLD00-01331
| FIRE-Final Inspection | 9/21/2000 | 9/21/2000 | 9/22/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/21/2000 at 08:00:57. Contact: ###-####.
|
FIR99-00669
| INSP-Sprinkler Rough-in | 9/18/2000 | 9/21/2000 | 9/21/2000 12:00:00 AM | A | PART |
|
|
###-#### tested the fire pump; 500 gpm pump tested at 150, 100 percent and churn; flushed dry standpipe at roof outlet; alarms not complete and will retest for alarms when they are complete 9/21/2000 9:13:56 AM
|
BLD99-01573
| FIRE-Final Inspection | 9/20/2000 | 9/21/2000 | 9/21/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 07:28:04. Contact: ###-####. sprinkler heads painted basement; penetrations; 9/22/2000 10:59:43 AM
|
BLD99-00199
| FIRE-Final Inspection | 9/20/2000 | 9/21/2000 | 9/21/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 07:30:28. Contact: ###-####.
|
BLD99-02762
| FIRE-Final Inspection | 9/20/2000 | 9/21/2000 | 9/21/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 07:41:06. Contact: ###-####.
|
BLD00-02095
| FIRE-Final Inspection | 9/20/2000 | 9/21/2000 | 9/21/2000 12:00:00 AM | P | PASS |
|
|
FIRE FN-- EARLE--###-####
|
BLD99-02186
| FIRE-Final Inspection | 9/20/2000 | 9/21/2000 | 9/21/2000 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 13:40:21. Contact: ###-####. need alarm plans; heat in building and riser room 9/22/2000 11:01:22 AM
|