FIR09-00550
| INSP-Final Inspection | 9/21/2009 | 9/21/2009 | 9/22/2009 8:09:45 AM | P | NH |
|
|
Scheduled by a contractor via Hello! on 9/21/2009 at 7:54:54 AM. Contact: ###-####.
|
FIR09-00226
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 8:09:24 AM | A | FAIL |
|
|
Smoke alarms must be interconnected per IFC requirements- see fire code review note #29. Notification tested okay.
|
FIR09-00224
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 8:02:29 AM | A | FAIL |
|
|
Smoke alarms need to be located away from supply or return air diffusers to avoid a delay in operation a min. of 3' per NFPA 72 -see fire code review notes item #3. Notification tested okay.
|
FIR09-00223
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 8:02:04 AM | A | FAIL |
|
|
Smoke alarms need to be located away from supply or return air diffusers to avoid a delay in operation a min. of 3' per NFPA 72 -see fire code review notes item #3. Notification tested okay.
|
FIR09-00222
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 8:01:41 AM | A | FAIL |
|
|
Smoke alarms need to be located away from supply or return air diffusers to avoid a delay in operation a min. of 3' per NFPA 72 -see fire code review notes item #3. Notification tested okay.
|
FIR09-00213
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 8:00:49 AM | A | FAIL |
|
|
Smoke alarms need to be located away from supply or return air diffusers to avoid a delay in operation a min. of 3' per NFPA 72 -see fire code review notes item #3. Notification tested okay.
|
FIR09-00216
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 8:00:04 AM | A | FAIL |
|
|
Smoke alarms need to be located away from supply or return air diffusers to avoid a delay in operation a min. of 3' per NFPA 72 -see fire code review notes item #3. Notification tested okay.
|
BLD09-01289
| FIRE-Final Inspection | 9/21/2009 | 9/21/2009 | 9/22/2009 7:43:45 AM | P | PART |
|
|
Fire life safety for the second floor remodel is acceptable, final pending completion of the scope of work for the project attatched fire sprinkler permit which includes heads at a new freezer in the warehouse area not yet installed.
|
FIR09-00413
| INSP-Sprinkler Rough-in | 9/21/2009 | 9/21/2009 | 9/22/2009 7:41:32 AM | P | PART |
|
|
Overhead rough-in at the board room, file room and reception area as marked on the stamped plan set are good for cover at the sheetrock ceilings. Breakroom partial cover okayed as one branchline is incomplete.
|
FIR09-00205
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:37:56 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
FIR09-00221
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:37:23 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
FIR09-00220
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:37:00 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
FIR09-00219
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:36:38 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
FIR09-00218
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:36:12 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
FIR09-00217
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:35:43 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
FIR09-00215
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:35:04 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
FIR09-00214
| INSP-Final Inspection | 9/15/2009 | 9/21/2009 | 9/22/2009 7:34:36 AM | A | PASS |
|
|
Fire alarm work passed field testing, permit finaled.
|
BLD09-01490
| FIRE-Final Inspection | 9/21/2009 | 9/21/2009 | 9/21/2009 2:54:29 PM | P | PASS |
|
|
Items on correction notice verified for compliance, life safety passed.
|
BLD09-01405
| FIRE-Final Inspection | 9/18/2009 | 9/21/2009 | 9/21/2009 11:01:59 AM | A | FAIL |
|
|
Correction items noted at the previous inspection are not done, project is not in condition for final at this time.
|
BLD09-00905
| FIRE-Final Inspection | 9/18/2009 | 9/21/2009 | 9/21/2009 11:00:26 AM | A | PASS |
|
|
Fire life safety inspection passed for both remodeled units.
|