BLD09-00858
| FIRE-Final Inspection | 9/21/2009 | 9/21/2009 | 9/22/2009 10:29:59 AM | P | PASS |
|
|
Life safety passed. Per Mark Sentenno a racking permit will not be required. All other items have been addressed.
|
FIR09-00571
| INSP-Sprinkler Rough-in | 9/21/2009 | 9/21/2009 | 9/21/2009 3:46:07 PM | P | PASS |
|
|
The sprinkler piping is ok to cover.
|
FIR09-00456
| INSP-Final Inspection | 9/21/2009 | 9/21/2009 | 9/21/2009 3:45:33 PM | P | PASS |
|
|
Permit finaled
|
FIR07-01032
| INSP-Sprinkler Rough-in | 9/17/2009 | 9/21/2009 | 9/21/2009 3:43:43 PM | P | CANC |
|
|
Duplicate inspection
|
FIR07-01032
| INSP-Sprinkler Rough-in/Hydro | 9/17/2009 | 9/21/2009 | 9/21/2009 3:42:32 PM | P | PASS |
|
|
Overhead hydro test passed.
|
FIR07-01031
| INSP-Sprinkler Rough-in/Hydro | 9/17/2009 | 9/21/2009 | 9/21/2009 3:39:14 PM | P | PASS |
|
|
Overhead hydo test passed.
|
BLD09-01489
| FIRE-Final Inspection | 9/18/2009 | 9/21/2009 | 9/21/2009 3:38:25 PM | A | PASS |
|
|
Life safety passed
|
BLD09-01552
| FIRE-Final Inspection | 9/21/2009 | 9/21/2009 | 9/21/2009 1:50:59 PM | P | PASS |
|
|
Life safety passed.
|
FIR09-00150
| INSP-Final Inspection | 9/16/2009 | 9/21/2009 | 9/21/2009 10:47:28 AM | A | FAIL |
|
|
No real inspection was started. The most up to date plans showing the plan modification/audio visuals was not on site. The batteries in the FACP are incorrect. Dave was going to cordinate with Treasure Valley Fire to test the alarm valve interconnection. The trouble monitor module located at the remote power supply has not been installed. No other items have been tested or inspected.
|