Inspections for the day of: Monday, September 21, 2009.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD09-00858 FIRE-Final Inspection9/21/20099/21/20099/22/2009 10:29:59 AMPPASS
Life safety passed. Per Mark Sentenno a racking permit will not be required. All other items have been addressed.
FIR09-00571 INSP-Sprinkler Rough-in9/21/20099/21/20099/21/2009 3:46:07 PMPPASS
The sprinkler piping is ok to cover.
FIR09-00456 INSP-Final Inspection9/21/20099/21/20099/21/2009 3:45:33 PMPPASS
Permit finaled
FIR07-01032 INSP-Sprinkler Rough-in9/17/20099/21/20099/21/2009 3:43:43 PMPCANC
Duplicate inspection
FIR07-01032 INSP-Sprinkler Rough-in/Hydro9/17/20099/21/20099/21/2009 3:42:32 PMPPASS
Overhead hydro test passed.
FIR07-01031 INSP-Sprinkler Rough-in/Hydro9/17/20099/21/20099/21/2009 3:39:14 PMPPASS
Overhead hydo test passed.
BLD09-01489 FIRE-Final Inspection9/18/20099/21/20099/21/2009 3:38:25 PMAPASS
Life safety passed
BLD09-01552 FIRE-Final Inspection9/21/20099/21/20099/21/2009 1:50:59 PMPPASS
Life safety passed.
FIR09-00150 INSP-Final Inspection9/16/20099/21/20099/21/2009 10:47:28 AMAFAIL
No real inspection was started. The most up to date plans showing the plan modification/audio visuals was not on site. The batteries in the FACP are incorrect. Dave was going to cordinate with Treasure Valley Fire to test the alarm valve interconnection. The trouble monitor module located at the remote power supply has not been installed. No other items have been tested or inspected.