ESC12-00630
| Site Preparation | 9/21/2012 | 9/21/2012 | 9/21/2012 4:51:54 PM | P | PART |
|
|
Excavation work in progress. Will need to sweep all hardsurfaces as needed to avoid trackout and at end of work day.
|
ESC12-00629
| Site Preparation | 9/21/2012 | 9/21/2012 | 9/21/2012 4:51:40 PM | P | PART |
|
|
Excavation work in progress. Will need to sweep all hardsurfaces as needed to avoid trackout and at end of work day.
|
ESC12-00628
| Site Preparation | 9/21/2012 | 9/21/2012 | 9/21/2012 4:51:25 PM | P | PART |
|
|
Excavation work in progress. Will need to sweep all hardsurfaces as needed to avoid trackout and at end of work day.
|
BLD12-01591
| BLD-Footing | 9/20/2012 | 9/21/2012 | 9/21/2012 4:51:09 PM | P | PASS |
|
|
Phone #: 2089410987 >> Inspection requested via mobile web by Bill
|
BLD12-01590
| BLD-Footing | 9/20/2012 | 9/21/2012 | 9/21/2012 4:50:33 PM | P | PASS |
|
|
Phone #: 2089410987 >> Inspection requested via mobile web by Bill
|
BLD12-01589
| BLD-Footing | 9/20/2012 | 9/21/2012 | 9/21/2012 4:49:58 PM | P | PASS |
|
|
Phone #: 2089410987 >> Inspection requested via mobile web by Bill
|
ESC12-00631
| Site Preparation | 9/21/2012 | 9/21/2012 | 9/21/2012 4:49:24 PM | P | PART |
|
|
Excavation work in progress. Will need to sweep all hardsurfaces as needed to avoid trackout and at end of work day.
|
BLD12-01592
| BLD-Footing | 9/20/2012 | 9/21/2012 | 9/21/2012 4:47:04 PM | P | PASS |
|
|
Phone #: 2089410987 >> Inspection requested via mobile web by Bill
|
BLD12-01822
| BLD-Final | 9/20/2012 | 9/21/2012 | 9/21/2012 3:11:14 PM | P | FAIL |
|
|
Eric Phone #: ###-####. Provide passage hardware on door to storage room.
|
BLD12-01824
| BLD-Final | 9/20/2012 | 9/21/2012 | 9/21/2012 3:10:56 PM | P | FAIL |
|
|
Eric Phone #: ###-####. Provide passage hardware on door to storage room.
|
BLD12-00043
| BLD-Energy code compliance | 9/21/2012 | 9/21/2012 | 9/21/2012 2:53:13 PM | P | PASS |
|
|
Brett Phone #: ###-####
|
ESC12-00018
| Random Inspection | 9/21/2012 | 9/21/2012 | 9/21/2012 2:53:02 PM | P | PASS |
|
|
|
ESC12-00581
| Site Final | 9/21/2012 | 9/21/2012 | 9/21/2012 2:52:50 PM | P | DONE |
|
|
|
ESC12-00581
| DOC - Permit Finaled | 9/21/2012 | 9/21/2012 | 9/21/2012 2:52:38 PM | P | PASS |
|
|
|
BLD12-01518
| BLD-Final | 9/21/2012 | 9/21/2012 | 9/21/2012 2:52:26 PM | P | FAIL |
|
|
jason Phone #: ###-####. Provide tempered glazing by rear slider, Provide CO2/SD outside master bedroom, provide code compliant stairs from garage door to house and provide blower door test results or third party inspection check list.
|
ESC12-00536
| Random Inspection | 9/21/2012 | 9/21/2012 | 9/21/2012 1:32:47 PM | P | PASS |
|
|
|
BLD12-01382
| BLD-Wall Bracing | 9/21/2012 | 9/21/2012 | 9/21/2012 1:32:33 PM | P | CANC |
|
|
Interior Sheet rock at Fire wall. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin. No fire wall on this unit.
|
ESC12-00535
| Random Inspection | 9/21/2012 | 9/21/2012 | 9/21/2012 1:31:01 PM | P | PASS |
|
|
|
BLD12-01383
| BLD-Wall Bracing | 9/21/2012 | 9/21/2012 | 9/21/2012 1:30:48 PM | P | PASS |
|
|
Interior Sheet rock at Fire wall. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin.
|
ESC12-00692
| Random Inspection | 9/21/2012 | 9/21/2012 | 9/21/2012 1:29:56 PM | P | PASS |
|
|
|
BLD12-01767
| BLD-Energy code compliance | 9/21/2012 | 9/21/2012 | 9/21/2012 1:29:30 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
ESC12-00610
| Tracking Control | 9/21/2012 | 9/21/2012 | 9/21/2012 11:59:15 AM | A | PART |
|
|
Excavation work in progress. Contractor to swepp all hard surfaces as needed and at end of work day.
|
ESC12-00609
| Tracking Control | 9/21/2012 | 9/21/2012 | 9/21/2012 11:58:53 AM | A | PART |
|
|
Excavation work in progress. Contractor to swepp all hard surfaces as needed and at end of work day.
|
ESC12-00608
| Tracking Control | 9/21/2012 | 9/21/2012 | 9/21/2012 11:58:35 AM | A | PART |
|
|
Excavation work in progress. Contractor to swepp all hard surfaces as needed and at end of work day.
|
ESC12-00607
| Tracking Control | 9/21/2012 | 9/21/2012 | 9/21/2012 11:58:20 AM | A | PART |
|
|
Excavation work in progress. Contractor to swepp all hard surfaces as needed and at end of work day.
|
BLD12-01571
| BLD-Energy code compliance | 9/20/2012 | 9/21/2012 | 9/21/2012 11:57:13 AM | A | PASS |
|
|
Steve Phone #: ###-####. Rigid foam insulation on interior side of stemwall under slab on grade.
|
BLD12-01570
| BLD-Energy code compliance | 9/20/2012 | 9/21/2012 | 9/21/2012 11:56:56 AM | A | PASS |
|
|
Steve Phone #: ###-####. Rigid foam insulation on interior side of stemwall under slab on grade.
|
BLD12-01569
| BLD-Energy code compliance | 9/20/2012 | 9/21/2012 | 9/21/2012 11:56:38 AM | A | PASS |
|
|
Steve Phone #: ###-####. Rigid foam insulation on interior side of stemwall under slab on grade.
|
BLD12-01568
| BLD-Energy code compliance | 9/20/2012 | 9/21/2012 | 9/21/2012 11:56:11 AM | A | PASS |
|
|
Steve Phone #: ###-####. Rigid foam insulation on interior side of stemwall under slab on grade.
|
BLD12-02043
| BLD-Framing/Rough-in | 9/20/2012 | 9/21/2012 | 9/21/2012 11:53:17 AM | A | PASS |
|
|
If possible late morning, please call Dan 20 minutes prior to arrival. Thanks Phone #: ###-#### >> Inspection requested via web by Dan Elser. Exterior wood framed wall and header for new opening ok.
|
BLD12-02390
| BLD-Foundation | 9/20/2012 | 9/21/2012 | 9/21/2012 11:35:27 AM | A | PASS |
|
|
Larry - ###-####
|