ELE16-01667
| Conference | 9/21/2016 | 9/21/2016 | 9/21/2016 2:11:27 PM | P | DONE |
|
|
Had talked to Rock about access to split system heating above hard lid with access door.Need some clarification on working accessibility. Phone #: ###-#### Inspection requested via web by Tom Betty Manufacturers specs call for minimum 18" of working clearance for access panel.
|
ELE16-02821
| Electrical Rough-In | 9/21/2016 | 9/21/2016 | 9/21/2016 12:54:49 PM | P | PASS |
|
|
Potting and equle // Kevin Phone #: ###-#### ok cover
|
ELE16-02513
| Electrical Rough-In | 9/21/2016 | 9/21/2016 | 9/21/2016 12:14:59 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rick Beckman ok cover
|
ELE16-02126
| Electrical Rough-In | 9/21/2016 | 9/21/2016 | 9/21/2016 11:49:09 AM | P | PASS |
|
|
Rough in inspection for basement only -- Final for upstairs not ready yet -- Phone #: ###-#### Inspection requested via web by Kendra Lanham rough in ok
|
ELE16-03053
| Temporary Service | 9/20/2016 | 9/21/2016 | 9/21/2016 11:41:27 AM | P | PASS |
|
|
Heather Stuckart will be your contact for this project ###-####. Please give her a call if you have any questions as she may not be on the job site. Thank you and have a super day! Phone #: ###-#### Inspection requested via web by Laura Longshaw t/s o/h n ok
|
ELE16-02855
| Final | 9/20/2016 | 9/21/2016 | 9/21/2016 11:33:10 AM | P | CANC |
|
|
I will call and Schedule a time to meet you onsite. Phone #: ###-#### Inspection requested via web by Matthew Dunay 1 solar panel broke during install, ordering new one.
|
ELE16-02428
| Final | 9/21/2016 | 9/21/2016 | 9/21/2016 11:30:16 AM | P | PASS |
|
|
Ron Phone #: ###-#### final ok
|
ELE16-01137
| Final | 9/14/2016 | 9/21/2016 | 9/21/2016 11:06:33 AM | A | PASS |
|
|
Home owner will be home between 10:30-1:30 if that works please Phone #: ###-#### Inspection requested via web by John VanZandt final ok
|
ELE16-02787
| Final | 9/15/2016 | 9/21/2016 | 9/21/2016 9:47:42 AM | A | PASS |
|
|
Final inspection please for this location. Please contact Rex Neilson at ###-#### 30 minutes prior to arrival so he can meet you there to let you in. David Forbes was the journeyman on the project and if you have any question please call him at ###-####. Thank you and have a super day! Phone #: ###-#### Inspection requested via web by Laura Longshaw final ok
|
ELE16-03063
| Temporary Service | 9/20/2016 | 9/21/2016 | 9/21/2016 9:47:41 AM | A | PASS |
|
|
Temp Pole is located behind trash enclosure on the south side of lot. Phone #: ###-#### Inspection requested via web by Ben Archibald t/s u/g n ok
|
ELE16-03062
| Electrical Rough-In | 9/20/2016 | 9/21/2016 | 9/21/2016 8:59:13 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ben Archibald ok to cover
|
ELE16-03050
| Electrical Rough-In | 9/21/2016 | 9/21/2016 | 9/21/2016 8:50:28 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Randy Fletcher rough in ok
|
ELE16-03051
| Electrical Rough-In | 9/20/2016 | 9/21/2016 | 9/21/2016 8:32:01 AM | A | PASS |
|
|
Swimming pool partial underground and bonding Phone #: ###-#### Inspection requested via web by Lars Johnson As per Lars Johnson, 2 bonds at auto cover, bonded 2 lights at pool and 1 at hottub, pipe for lights stub in trench and other contractor is running pipe back to pool equipt room, bond for 1 ladder and a bond for 2 handrails, also 2 bonds for handicapped lifts.
|
ELE12-03157
| Final | 9/20/2016 | 9/21/2016 | 9/21/2016 7:29:31 AM | A | PASS |
|
|
Marco Phone #: ###-#### looked at job for final on 9/20/16. Homeowner called it in but it didnt go through for some reason.
|
ELE16-03063
| Temporary Service | 9/20/2016 | 9/21/2016 | 9/20/2016 10:45:36 PM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Ben Archibald Inspection cancelled from web by: Ben Archibald
|
ELE16-03050
| Electrical Rough-In | 9/20/2016 | 9/21/2016 | 9/20/2016 10:12:43 AM | A | CANC |
|
|