Inspections for the day of: Wednesday, September 21, 2016.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-03207 FIRE-Final Inspection9/20/20169/21/20169/21/2016 4:32:11 PMPCANC
Inspection request was for convention center side of building, this inspection request is cancelled.
BLD15-02494 FIRE-Final Inspection9/20/20169/21/20169/21/2016 4:31:16 PMPPART
Partial life fire safety inspection complete. Fire sprinkler inspection complete for level 5 wet system, level 4 wet system, level 3 dry system, level 2 wet system, level 2 dry system and level 1 elevator lobby, fire sprinklers systems noted will be active before TCO. Fire alarm inspection complete for same area's as fire sprinklers, noted as well that fire alarms for these area's will be active before TCO. Fire extinguishers are in place with current inspection tags on level 5, level 4 and level 1 elevator lobby. Life fire safety inspection complete for level 5, level 4, level 3 parking and level 2 parking. Remaining levels 1 and 2 of convention center will be inspected at a later date.
FIR15-00727 INSP-Final Inspection9/20/20169/21/20169/21/2016 4:23:48 PMAPART
Partial final for convention center fire sprinkler systems, area's complete are level 5, level 4, level 2 and level 1 lobby. Dry systems for level 3 and level 2 complete and in service. Level 1 fire sprinkler system will be inspected (excluding level 1 elevator lobby, sprinklers for this area complete)
FIR16-00427 INSP-Supply line flush9/20/20169/21/20169/21/2016 1:25:20 PMPCANC
I called and left a message with point of contact Scott Phone #: ###-#### , appears that a SUEZ representative is not scheduled to perform flush (I spoke to SUEZ and it was not on their schedule), main line underground flush will not be completed until a SUEZ representative is schedule to operate underground valve to perform mainline flush. This inspection request is cancelled and a new underground flush request will need to be rescheduled with a SUEZ rep to operate valve.
FIR15-00602 INSP-Sprinkler Rough-in9/15/20169/21/20169/21/2016 12:01:43 PMPDONE
Fire pump start up complete
FIR15-00767 INSP-Final Inspection9/20/20169/21/20169/21/2016 11:08:39 AMAPASS
Final fire alarm inspection passed/complete.
FIR16-00558 INSP-Final Inspection9/20/20169/21/20169/21/2016 9:53:40 AMAPASS
Final fire alarm inspection passed/complete.
BLD16-02659 FIRE-Final Inspection9/20/20169/21/20169/21/2016 8:26:34 AMAPASS
Fire sprinkler inspection for area of work complete, no modifications to fire alarm system, fire extinguisher will be mounted in discussed location. Final life fire safety inspection passed/complete.
FIR16-00520 INSP-Final Inspection9/21/20169/21/20169/21/2016 8:25:11 AMAPASS
Final fire sprinkler inspection passed/complete
FIR08-00825 INSP-Final Inspection9/20/20169/21/20169/20/2016 3:33:18 PMACANC
Incorrect inspection request