Inspections for the day of: Thursday, September 22, 2005.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00089 INSP-Sprinkler Rough-in/Hydro9/22/20059/22/20059/22/2005 3:30:04 PMPCANC
Wrong permit called in, this inspection was for tenant P.F. Chang's FIR05-00378, not the core and shell.
FIR05-00301 INSP-Final Inspection9/22/20059/22/20059/22/2005 3:27:03 PMPFAIL
Power to one electrical box below hood failed to shut down upon system activation, per contractor, the wiring to this box is to be removed. Need verification of removal for final.
FIR05-00442 INSP-Final Inspection9/22/20059/22/20059/22/2005 2:37:45 PMPPART
Overhead fire sprinkler rough-in is good for cover, some areas in the two south apartments already covered, heads in the washer/dryer closets need correct temperature rating.
BLD05-01993 FIRE-Final Inspection9/21/20059/22/20059/22/2005 11:06:20 AMAPART
Fire life safety passed inspection, final pending approval of sprinkler modifications on resubmittals. A temporary occupancy was approved with Sam Rogers permission pending sprinkler sign off.
BLD05-02207 FIRE-Final Inspection9/21/20059/22/20059/22/2005 10:08:15 AMAFAIL
Provide address and suite numbers, remove manual thumbturns on main entry/exit doors and provide ADA hardware, provide inspection certification tag for fire extinguisher.
FIR05-00510 INSP-Final Inspection9/21/20059/22/20059/22/2005 9:40:51 AMAPASS
Fire alarm passed inspection, permit finaled.
BLD05-01314 FIRE-Final Inspection9/22/20059/22/20059/22/2005 12:00:00 AMAFAIL
Remove keyed locking hardware at the intermediate door in pharmacy, fire sprinkler is overspaced due to the new wall - a fire sprinkler permit will be required for any modifications.
FIR05-00521 INSP-Final Inspection9/22/20059/22/20059/22/2005 12:00:00 AMAPART
Modifications have been completed, approval pending resubmittals.
FIR05-00287 INSP-Final Inspection9/22/20059/22/20059/22/2005 12:00:00 AMPPASS
Fire sprinkler permit finaled.
FIR05-00378 INSP-Sprinkler Rough-in9/22/20059/22/20059/22/2005 12:00:00 AMPPART
Overhead rough-in is okay for cover in the grid ceiling areas, will verify proper spacing and head temp. ratings at heat sources in the kitchen after all drops have been cut in. One branch line is directly over an electrical panel, this will need to be relocated per electrical code.