FIR14-00068
| INSP-Sprinkler Rough-in | 9/19/2014 | 9/22/2014 | 9/22/2014 4:02:29 PM | P | PART |
|
|
Completed inspection for remainder of UG fire supply line to the point of connection. * Note: Field install does not match approved plans- two 45's have been added and the PIV as shown has been deleted. Need to provide a plan modification prior to final. Verified thrust blocking, tracer, piping, bury depth, etc.
|
FIR14-00365
| INSP-Sprinkler Rough-in | 9/19/2014 | 9/22/2014 | 9/22/2014 3:56:49 PM | A | PART |
|
|
Inspection for cover at the 2nd and 3rd floor service elevator lobby drop ceilings and 2nd level 3" dry main at west side heilix. Discussed project schedule and work completed to date.
|
FIR14-00591
| INSP-Sprinkler Rough-in | 9/19/2014 | 9/22/2014 | 9/22/2014 11:12:53 AM | A | PART |
|
|
Overhead work at the grid ceilings approved for cover. Pendent head at the intersection of hall 1 and hall 2 must meet NFPA 13 table 8.6.5.1.2.
|