BLD14-02146
| FIRE-Final Inspection | 9/19/2014 | 9/22/2014 | 9/23/2014 9:03:33 AM | A | PASS |
|
|
Life safety passed
|
BLD14-01165
| FIRE-Final Inspection | 9/22/2014 | 9/22/2014 | 9/22/2014 3:22:42 PM | P | FAIL |
|
|
Provide single action hardware on all doors. All other items appear ok.
|
FIR14-00544
| INSP-Sprinkler Rough-in/Hydro | 9/19/2014 | 9/22/2014 | 9/22/2014 3:21:54 PM | P | CANC |
|
|
Cancel per Richard
|
FIR14-00569
| INSP-Sprinkler Rough-in/Hydro | 9/19/2014 | 9/22/2014 | 9/22/2014 2:11:34 PM | P | CANC |
|
|
Cancel per Mike due to no access to riser because of concrete and United Water has not turned on the site water yet.
|
FIR14-00471
| INSP-Sprinkler Rough-in | 9/19/2014 | 9/22/2014 | 9/22/2014 11:50:33 AM | A | PASS |
|
|
Combustible concealed spaces are ok to cover. They have been filled with insulation.
|
FIR13-00723
| INSP-Final Inspection | 9/19/2014 | 9/22/2014 | 9/22/2014 10:34:39 AM | A | PART |
|
|
Forward flush passed and the alarm bell functioned. Need the work in the existing building completed.
|
FIR14-00448
| INSP-Sprinkler Rough-in | 9/19/2014 | 9/22/2014 | 9/22/2014 10:30:10 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered.
|
FIR14-00585
| INSP-Alarm Testing | 9/19/2014 | 9/22/2014 | 9/22/2014 10:29:28 AM | A | DONE |
|
|
FACP interconnection with the new canopy dry system passed. Included low air, water flow and tamper switches.
|
FIR14-00339
| INSP-Final Inspection | 9/19/2014 | 9/22/2014 | 9/22/2014 10:27:45 AM | A | PASS |
|
|
Permit finaled.
|