Inspections for the day of: Wednesday, September 23, 2009.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00468 INSP-Final Inspection9/22/20099/23/20099/24/2009 12:06:32 PMPFAIL
Inspection was inadvertantly called in for a final but this turned into a conference. Per Mark, with simplexgrinnell the elevator recall controls will not be installed at this time but infact will be installed some time within the next three years. Per stephanie the modules that interconnect the elevator controls with the new FACP are to be removed and as-builts provided to the fire inspector. A separate FIR permit will be requird in the future for the monitoring of the elevator recall functions.
FIR09-00490 INSP-Sprinkler Rough-in9/23/20099/23/20099/23/2009 3:25:17 PMPPART
Rough-in is passed except for a small combustible concealed area that has been marked on the approved plans that lacks upright sprinkler coverage. This area will be checked at the final. Piping can be covered.
FIR09-00291 INSP-Conference9/23/20099/23/20099/23/2009 2:58:31 PMPDONE
Discussed dry pendant sprinkler spacing in the coolers.
FIR09-00565 INSP-Final Inspection9/21/20099/23/20099/23/2009 1:39:53 PMACANC
Rescheduled for friday morning.
FIR09-00415 INSP-Final Inspection9/21/20099/23/20099/23/2009 1:39:34 PMACANC
Rescheduled for friday morning.
BLD09-01062 FIRE-Final Inspection9/23/20099/23/20099/23/2009 12:43:22 PMPPASS
Life safety passed.
FIR09-00451 INSP-Final Inspection9/23/20099/23/20099/23/2009 12:42:51 PMPPASS
Permit finaled
FIR08-00830 INSP-Sprinkler Rough-in/Hydro9/22/20099/23/20099/23/2009 11:34:36 AMAPASS
The 24 hour air test on the first floor dry pipe riser passed test.
BLD09-01482 FIRE-Final Inspection9/22/20099/23/20099/23/2009 10:44:42 AMAPASS
Life safety passed. Correct hardware was being installed on the warehouse as I left
BLD09-01483 FIRE-Final Inspection9/22/20099/23/20099/23/2009 10:40:13 AMAPASS
life safety passed
FIR09-00532 INSP-Final Inspection9/22/20099/23/20099/23/2009 8:56:53 AMAPASS
Permit finaled.