PLM08-01020
| Final | 9/24/2008 | 9/24/2008 | 9/24/2008 3:42:20 PM | P | PASS |
|
|
|
PLM08-01064
| Final | 9/22/2008 | 9/24/2008 | 9/24/2008 3:12:34 PM | P | PART |
|
|
Internet Inspection Request from: Ina Schneider 120 deg. max hot water to public lavs. temp occ ok.
|
PLM08-02296
| Sprinkler (Final) | 9/23/2008 | 9/24/2008 | 9/24/2008 2:36:57 PM | P | PART |
|
|
trish Phone #: ###-#### tie in ok
|
PLM08-02186
| Water and/or Sewer | 9/24/2008 | 9/24/2008 | 9/24/2008 2:12:05 PM | P | PASS |
|
|
Randy- late pm please Phone #: ###-#### water line ok may add sprinkler later.
|
PLM08-02213
| Roof Drains | 9/24/2008 | 9/24/2008 | 9/24/2008 1:44:30 PM | P | PART |
|
|
jim Phone #: ###-#### rain drain branches in courtyard north side ok
|
PLM08-01606
| Plumbing Rough-in | 9/24/2008 | 9/24/2008 | 9/24/2008 1:28:14 PM | P | PASS |
|
|
Brett Phone #: ###-#### ri ok
|
PLM08-02221
| Plumbing Rough-in | 9/24/2008 | 9/24/2008 | 9/24/2008 9:57:07 AM | A | PASS |
|
|
ri ok
|
PLM08-02289
| Groundwork | 9/23/2008 | 9/24/2008 | 9/24/2008 9:40:14 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 9/23/2008 at 8:05:46 PM. Contact: ###-####.
|
PLM08-01539
| PLM-Aging Inspection | 9/24/2008 | 9/24/2008 | 9/24/2008 9:12:00 AM | | PASS |
|
|
wip
|
PLM08-01033
| PLM-Aging Inspection | 9/24/2008 | 9/24/2008 | 9/24/2008 9:10:15 AM | | PASS |
|
|
|
PLM08-01033
| Final | 9/24/2008 | 9/24/2008 | 9/24/2008 9:09:58 AM | P | PASS |
|
|
|
PLM08-02234
| Plumbing Rough-in | 9/23/2008 | 9/24/2008 | 9/24/2008 8:57:02 AM | A | PASS |
|
|
call ###-#### for any questions. thank you Phone #: ###-#### Internet Inspection Request from: Mike Dunson
|
PLM08-02294
| Water and/or Sewer | 9/23/2008 | 9/24/2008 | 9/23/2008 3:19:27 PM | A | PASS |
|
|
As early as possible, if you can. Thanks!! Phone #: ###-#### Internet Inspection Request from: Leanne Ruzicka
|