FIR14-00344
| INSP-Sprinkler Rough-in | 9/23/2014 | 9/24/2014 | 9/24/2014 4:58:45 PM | P | PART |
|
|
Completed rough-in for the remainder of 3rd floor area C. Items noted include; SW heads at six locations are not installed or piped, repair damaged hanger, plan modification will be necessary for changes to pipe routing and type at the trash, storage, elev. lobby, houskeeping, and adjacent hallway areas, tenting at some locations adjusted while on site. Ref. plans for annotations.
|
FIR14-00604
| INSP-Sprinkler Rough-in | 9/23/2014 | 9/24/2014 | 9/24/2014 4:53:07 PM | P | FAIL |
|
|
Correction items noted for the remainder of dry system install at C wing include; missing hanger at 2 1/12" main, roof hatch enclosure will obstruct upright coverage, one SD attic head is overspaced, 11 ssu heads are overspaced at deck elevation change, two missing sprigs and heads at east overbuild, blocked upright at truss shear.
|
FIR14-00478
| INSP-Sprinkler Rough-in | 9/24/2014 | 9/24/2014 | 9/24/2014 4:46:32 PM | P | PART |
|
|
UG fire supply line including the IBR, thrust block and stub to a point 14' beyond the stem wall approved for bury.
|
FIR13-00725
| INSP-Conference | 9/24/2014 | 9/24/2014 | 9/24/2014 10:45:26 AM | A | DONE |
|
|
|
BLD14-02496
| FIRE-Final Inspection | 9/24/2014 | 9/24/2014 | 9/24/2014 10:44:49 AM | A | PART |
|
|
PFE on site, final pending hardware and signage per previous inspection.
|