Inspections for the day of: Wednesday, September 25, 2002.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBill VanDegrift
TitlePLM-INSPECTOR
Phone #794-9372
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM02-02539 Final9/24/20029/25/20029/25/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 09/24/2002 at 10:11:23. Contact: ###-####. final ok 9/25/2002 9:31:57 AM
PLM02-02539 Final9/24/20029/25/20029/25/2002 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 09/24/2002 at 10:11:23. Contact: ###-####. final ok 9/25/2002 9:31:57 AM
PLM02-02934 Plumbing Rough-in9/24/20029/25/20029/25/2002 12:00:00 AMANR
Phone #: ###-#### Internet Inspection Request from: Amy Lawson
PLM02-02936 Sprinkler (Final)9/24/20029/25/20029/25/2002 12:00:00 AMAPASS
mike- ###-####-for united water pump water
PLM01-03114 Water and/or Sewer9/25/20029/25/20029/25/2002 12:00:00 AMAPART
conference on sewer testing just needs west basement stub tested. 9/25/2002 9:25:31 AM
PLM01-03114 Water and/or Sewer9/25/20029/25/20029/25/2002 12:00:00 AMAPART
conference on sewer testing just needs west basement stub tested. 9/25/2002 9:25:31 AM
PLM01-03114 Water and/or Sewer9/25/20029/25/20029/25/2002 12:00:00 AMPCANC
dup. request 9/25/2002 10:12:02 AM
PLM02-02943 Sprinkler (Final)9/25/20029/25/20029/25/2002 12:00:00 AMPPASS
chad ###-####
PLM01-03114 Water and/or Sewer9/25/20029/25/20029/25/2002 12:00:00 AMPPASS
last sewer test ok 9/25/2002 1:07:49 PM
PLM01-03114 Water and/or Sewer9/25/20029/25/20029/25/2002 12:00:00 AMPPASS
last sewer test ok 9/25/2002 1:07:49 PM
PLM02-02934 Plumbing Rough-in9/25/20029/25/20029/25/2002 12:00:00 AMPNR
needs hangers and caps onthe abandoned vents 9/25/2002 2:26:09 PM
PLM02-00129 Final9/25/20029/25/20029/25/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 09/25/2002 at 07:32:41. Contact: ###-####.
PLM02-00179 Final9/25/20029/25/20029/25/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 09/25/2002 at 07:33:24. Contact: ###-####.
PLM02-00228 Final9/25/20029/25/20029/25/2002 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 09/25/2002 at 07:34:51. Contact: ###-####.
PLM02-02938 Sprinkler (Final)9/25/20029/25/20029/25/2002 12:00:00 AMPFAIL
###-#### 2 clamps at each joint rolled 180 deg apart are required, test pvb 9/25/2002 1:57:22 PM
PLM02-02939 Plumbing Rough-in9/25/20029/25/20029/25/2002 12:00:00 AMPPASS
r/i ryan ###-####